Activity Progress Dialog Box
Open Plan enables you to progress an activity by entering the physical percent complete (PPC) at either at the activity level or the resource level. You can status an activity using the Activity Progress dialog box.
Like the Activity Details dialog box, the Activity Progress dialog box is modeless, which allows you to keep it open while performing other operations in Open Plan. The navigation buttons and the Close, Undo, and Apply commands function identically to their counterparts in the Activity Details dialog box. You can, in fact, keep both the Activity Details dialog box and the Activity Progress dialog box open at the same time, updating the information in either dialog box as appropriate.
By default, Open Plan synchronizes multiple activity dialog boxes so that using the navigation buttons on one dialog box will result in Open Plan scrolling to the appropriate activity on another dialog box.
Tabs
The Activity Progress dialog box includes the following tabs:
- Activity tab: On the Activity tab, you can enter an actual start date and select one of the statusing methods.
- Resources tab: Enter resource progress information for actual and remaining usage at the same time regular activity progress information is entered.
- Notes tab: Create, edit, or delete a note attached to the activity.
The following buttons at the bottom of the Activity Progress dialog box apply to all tabs:
- Close: Closes the dialog box, saving any changes.
- Undo: Cancels any changes on this dialog box that have not been saved using the Apply button.
- Apply: Applies and saves changes on this dialog box, while leaving the dialog box open for further action. This button is disabled until changes are made.
- Help: Provides access to the online Help topic for the displayed tab.
A set of navigation controls allows you to select another activity.
| Button | Operation |
|---|---|
| Displays the first record | |
| Displays the previous record | |
| Displays the next record | |
| Displays the last record |
You can also use the following keys on your keyboard to navigate to another activity.
- CTRL+HOME: Displays the first activity.
- Page Up: Displays the previous activity.
- Page Down: Displays the next activity.
- CTRL+END: Displays the last activity.
Related Topics
Related Procedures
- Related Topics:
- Display the Activity Progress Dialog Box
Use this procedure to display the Activity Progress dialog box. - Activity Tab
In general, this tab allows you to specify the following information so that a revised time analysis of the project can be performed: - Resources Tab
In general, this tab enables you to enter resource progress information for actual and remaining usage at the same time that regular activity progress information is entered. - Notes Tab
This tab allows you to create, edit, or delete a note attached to the activity. - Steps Tab
Activity steps are similar to milestones and can add significant value to project scheduling. A scheduler can assign several steps to an activity and weight each step to apportion its value compared to other steps. Steps allow you to objectively measure the progress of an activity.