Change Activity Numbers of Time Entries
Use the Costs submodule to change the activity number of time entries in selected jobs.
To use the Costs submodule, you must have access to Jobs as defined in the User Access Rights submodule under Settings.
To change the activity number of a time entry:
- On the main toolbar, click Jobs .
- On the side toolbar, click Jobs List and highlight the job with the time entry that you want to change the activity number of.
- On the side toolbar, click Costs.
- Click the Hours tab.
- Highlight the time entry that you want to change the activity numbers of.
- Click and select Change activity number.
- In the Change Activity Number dialog box, double-click on the New activity field of the time entry that you want to change the activity number of and use the drop-down list to select a new activity.
- Click OK.
Parent Topic: Hours Tab