Add Resources to a Scrum Sprint

Use the Scrum Board submodule to add resources to a task in a scrum sprint.

  • To use Scrum Board, you must have access to Scheduling as defined in User Access Rights under Settings.

  • Before you can add resources to a task in a scrum sprint, the resources must have access to the job that is associated with the task.

To add resources to a scrum sprint:

  1. On the main toolbar, click Scheduling .
  2. In the left pane of the Scheduling page, click Schedule Overview > Scrum Board.
  3. Click the Scrum Board tab.
  4. On the tab toolbar, select a sprint from the drop-down list.
  5. In the grid, select the task to which you want to add the resource and click Add Resources on the tab toolbar.
  6. In the Resources dialog box, find the resource that you want to add and hover your mouse over the right edge of the resource until the drag marks appear (six dots), and drag it to a task in the grid.
  7. In the Add Resource to Task dialog box, make the necessary changes and click OK.