EAC Analysis Report Overview

This report helps you to determine the feasibility of your Estimated at Completion (EAC). You must have access rights to the Cost Analysis reports and the EAC Analysis report to see this report from the Reports section, or be given access to a dashboard with this report as a dashpart. The data that the EAC Analysis report displays is based on a control account or work package that is selected from the Cost Analysis form. It also allows you to select multiple control accounts or work packages. This report uses the master calendar.

Using this report, you can complete the following tasks:

Filtering the Data

You can specify either specific records or criteria when you define the filter that the system uses when creating the report. Click in the Selection column to display the Control Account Search Dialog Box.

For more information, see Modify Standard Reports and Specifying Criteria vs. Specific Records (Values).

Master Projects

If you select a master project in Project Search (<Report> Search dialog box), when the report runs, data for all subprojects related to the selected master project displays on the report.

The cost sets that are used (displayed on the Table Columns tab of the Options dialog box) are from the master project. You don't need to define the cost sets in each subproject. When you run the report, only the classes in the master project for the cost sets you have selected will be retrieved from each subproject. For example, if you select a cost set on the Table Columns tab that includes a budget class, when you run the report, it only retrieves the budget class data from each subproject.

Reports using master projects use the master calendar.

To display the data by project, group by Project on the Sorting/Grouping tab.

Report Options

You can use the Options dialog box to customize the report. Click in the Options column to display the EAC Analysis Options dialog box which includes the following tabs:

All tabs on the Options dialog box share some common options and buttons.

EAC Analysis Report Details

Aside from the project name and the control account information, this report displays the following information:

You cannot edit the columns that display on the EAC Analysis report.

The formulas used to calculate the metrics are displayed in the report header for your reference. For more information about the formulas, see Earned Value Management Field Descriptions and Formulas

The color banding for the VAC, SPI, and CPI columns are based on the settings made on the Thresholds tab of the Projects form. If the Use Color Banding option on the tab is not selected, the color banding on this report does not display.

Generate the Report

You can generate this report from the following areas:

What do you want to do?

Review the general report procedures (use, modify, edit, format, sort, and archive reports)

Select and display the report

Select an EAC cost set

Select the report currency

Set weighting options for Statistical EAC 4

Sort report data

Modify the report properties