The Schedule Analysis view enables you to view the work package to which an activity rolls into in the Cost Analysis view.
To view the work package linked to an activity in the Cost Analysis view, complete the following steps:
Display the Schedule Analysis view. How?
In the Schedule Analysis grid, select the activity that you want to display the associated work package for.
Click the General tab.
On the General tab of the Schedule Analysis view, click the work package link in the Work Package field in the Cost Links group box.
The Cost Analysis view for the work package linked to the activity displays.
Find activities that are not progressing according to plan
View resources assigned to an activity