Use the Schedule Analysis view to find activities that are not progressing as planned based on the activity dates.
You can use the Advanced display of the Activity Search dialog box to create a filter that enables you to view activities that are behind schedule. For example, you can create a filter that displays only those activities whose Expected Finish dates are behind schedule. For more information, see Search Overview.
To find activities that are not progressing according to plan, complete the following steps:
Display the Schedule Analysis view. How?
On the Schedule Analysis Form toolbar, click in the Search field.
On the Activity Search dialog box, select Advanced in the Display Type field.
Use the Search Criteria grid to create filters to display the activities that are not progressing according to plan.
After creating a filter, the Activity Search dialog box displays the activities that meet the filter criteria. Select the activities that you want to display on the Schedule Analysis form and click Select. If you want to display all activities returned by the filter, click Select All.
View the work package linked to an activity in the Cost Analysis view
View resources assigned to an activity
Learn how cost and schedule Progress entries are created