Progress Tab of the Projects Form

Use this tab to configure project-level settings applicable for updating progress. The settings are applicable to cost, schedule, or both.

Project-level vs. System-Level Settings

Many of the fields on this tab can also be seen on the System Settings Progress tab. The fields on this tab allow you to configure the settings on a project-by-project basis (project-level) whereas the fields on the System Settings Progress tab allow you to configure the settings for all projects (system-level).

The fields on this tab are disabled if Apply Progress Settings to All Projects is selected on the System Settings Progress tab. This indicates that the system-level settings are set to apply to all projects and you cannot override them for any one project.

Toolbar

All tabs of the Projects Form View share a common toolbar.

Source System to Update

Use the fields in this group box to specify whether progress is entered into the cost (work packages) or schedule (activities) system. If progress is entered into the schedule, any data found in the cost system is updated through processes in the cost system. For example, if the cost system is Cobra, the Integration Wizard is used to update the work packages from the progress that is entered on the activities through PM Compass.

If at least one unapproved progress entry exists in the system, you cannot change this field setting until all of the existing unapproved progress entries are approved or deleted.

Schedule Duration Unit

Select a default duration unit to display on the Enter Schedule Progress form. This is used when you have entered a duration amount without including a letter for the unit (such as "5w" or "3d"). This field is disabled when the Source System to Update is Cost.

Since the duration units in Primavera P6 are a user setting, PM Compass converts all durations to the units selected in this field.

Schedule Forecast Date Set

Select a date set when the schedule forecast start or finish date value is derived. The Forecast Finish field on the General tab of the Projects form derives its date value from this setting. This field is disabled when the Source System to Update is Cost.

If the forecast date column is visible in the Schedule Update Status/Approval form, the system uses this date setting. For example, if you select Early Date as the forecast date, the selected value becomes the default setting in the schedule view.

Microsoft Project and Deltek Open Plan have similar options.

Progress Cycle

Use the fields in this group box to specify the end date and length (frequency) of the progress cycle. The cost status date is displayed here for reference. These fields are disabled when the Source System to Update is Schedule.

Allowable Schedule Progress Types

Use these fields to select the progress types that PM Compass recognizes during progress update. All options that you select here become available in the Progress Type drop-down list on the General tab of the Enter Schedule Progress form.

This group box is disabled when the source system to update is Cost.

Options When Entering Cost or Schedule Progress

Use (as the administrator) the options in this group box to select the business checks or validations to implement when updating cost or schedule progress. These trigger a validation error, warning, or visual indication, and set defaults on the Update Progress form when rules or criteria are not met.

These settings are disabled when Apply Progress Settings to All Projects on the Progress Tab of the System Settings Form is selected.

Last Progress Submission Date Fields

This group box allows you to select which user date field from the cost or schedule contains the date when progress was last submitted for cost or schedule. Only date fields that have been added to user-defined data appear in the drop-down selection.  See Source Fields Tab of the User-Defined Data Form for information on how to add source fields.

What do you want to do?

Select a source system to update


View location

Learn more about...