Project Planning Performance

Use the Project Planning Performance report to review project plan schedules and all aspects of plan performance: history, forecasts, hours, costs, and profitability.

Match JTD Option

This report is affected by the Match JTD option, which you set on the Project Planning form.

For any plan that is mapped to a project, use the Match JTD option on the Default WBS Mapping dialog box in Planning to specify the level of matching between job-to-date information and work breakdown structure (WBS) levels. (To display that dialog box, click Default WBS Mapping on the Options menu on the Project Planning form.) When you select that option for a level, all subsequent levels are automatically selected. When a level is not selected, Vision calculates the job-to-date value as the sum of values from lower levels.

For example, suppose you have two plans, both of which are mapped to the same project. However, plan 1 is mapped to phase A of that project and plan 2 is mapped to phase B. If you select Match JTD for the phase level, Vision accumulates actual values at the phase level, rather than at the project level. As a result, the job-to-date values are accurate for each of the plans. If you do not select Match JTD for the phase level, Vision accumulates job-to-date values at the project level. In that case, job-to-date values for plan 1 could incorrectly include actual activity for phase B, and those for plan 2 could incorrectly include actual activity for phase A.

Access to Labor Cost Information

The Labor Cost Rates/Amounts option on the Accounting tab of the Roles form (Configuration > Security > Roles) determines your access to actual labor cost rates and amounts when you preview or print Planning reports. In some cases, it also determines your access to planned labor costs.

Configuration Settings

The contents of this report depend upon whether or not the following options are selected in the Planning Tabs group box on the General tab of the Plan Settings form (Configuration > Planning > Plan Settings):

  • Enable Expense Planning
  • Enable Consultant Planning
  • Enable Unit Planning

If Enable Unit Planning is not selected, actual hours and amounts for units are included in the expenses or consultants sections of the report.

Non-Work Days

When it calculates a plan's hours, cost amounts, or billing amounts, Vision takes into consideration the company's non-work days specified on the Holiday Configuration form (Configuration > General > Holiday Calendar).

When it prorates values and calculates standard hours, Vision takes into consideration the non-work days specified on the Holiday Configuration form for the company that was active when the plan was created.

If hours or amounts are posted to a span of non-work days or holidays and those non-work days fall completely within the start and end dates of a period column on the report, they are included on the report for that period. If the non-work days do not completely fall within a period column on the report (for example, if they fall within more than one report period), the proration process may exclude them from the report.

Sort and Group by Custom Fields

You can sort and group information on this report by custom fields for the top project of a plan.

Options Dialog Box

Use the Options dialog box to specify reporting options for a report. Depending on the report, the dialog box contains one or more of the following tabs: General, Sorting/Grouping, Columns, Budget, Metrics, User Defined Sections, Activity, Drill Down, Layout, and Graph.