Units Tab of the Plan Form

Use the Units tab on the Plan form to assign units to work breakdown structure (WBS) elements and to enter planned quantities for those unit assignments. As you enter unit quantities, the planning grid automatically updates totals and other summary values for the individual unit assignment and for each WBS element above the assignment in the plan structure.

This tab is available only if all of the following are true:
  • The Resource Planning module is activated.
  • In Settings > Resource Planning > Plan Settings, Unit Planning is enabled for the project's company.
  • Your security role gives you access to the Units tab.

Note that changes you make to a plan are saved automatically. However, until you publish the plan, you can click Other Actions > Revert on the Actions bar to discard all unpublished changes and restore the plan to its most recent published version.

In the upper-right corner of the Plan form, the Show field indicates whether the amounts in the middle grid section are displayed at cost or at billing. You can switch between Cost and Billing if both budget types are selected for the project plan on the General tab of the Plan Settings dialog box (Other Actions > Plan Settings). Your selection in this field does not affect what you see in the calendar period columns.

  • If the project is in a single currency database, the amounts that display on this tab, at either cost or billing, are in the same currency.
  • If the project is in a multicurrency database, the currency in use is indicated next to Cost or Billing in the Show field. The project currency is always used when you view the amounts at cost. The Use Billing (Not Project) Currency for Reporting option in Settings > Accounting > Labor Options determines whether or not the amounts change when you view the plan at billing. If the option is set to Yes, the amounts display in the billing currency. Otherwise, amounts continue to display in the project currency when you view the plan at either cost or billing.

Use the Units tab on the Plan Settings dialog box to specify the billing multiplier for units and to recalculate the planned unit cost or billing amounts with the current cost or billing rates in the unit table.

Contents: Above the Grid

Field Description

If the plan date range includes more than 30 calendar periods, based on your selection in Scale, you must use this date range selector to display some of those periods. Click or in the date range selector to load earlier or later sets of calendar periods. (You can also click the earliest or latest date in the date range selector to load a new set of periods.)

For example, if you click in the date range selector, Vantagepoint retains the most recent 15 of the currently loaded calendar periods and loads the next 15 later calendar periods so you can scroll them into view as well.

If 30 or fewer calendar periods exist in the plan date range, you can view all of them by scrolling the grid horizontally, so the date range selector does not display on the toolbar.

If WBS elements or assignments have actual and/or baseline data entered outside of the plan date range and you set to display actual and/or baseline sub-rows using the Sub-Row Selection dialog box ( > Sub-Row Selection), Vantagepoint displays additional calendar period columns to represent these amounts.

Click this icon to display the following options:
  • Column Settings: Select this option to determine how you want to display columns and WBS elements on the Units tab.
  • Sub-Row Selection: Select this option to include sub-rows for planned, actual, and baseline unit data in the calendar periods.

The columns and sub-rows that you can choose to display on the Units tab are determined by the selections of your system administrator in Settings > Resource Planning > Grids.

Contents: Left Grid Section

This section displays the elements in the plan WBS. You can assign units at each lowest-level element in a given branch of the plan WBS.

To change the width of the left grid section, position your cursor over the dividing line between the left grid section and the middle grid section and then drag the line.

Field Description
Level/Unit Name

This column displays the WBS elements and, for each lowest-level element, the currently assigned units. Use the arrows to expand and collapse the plan levels.

To add unit assignments, check out the plan, hover over the WBS row for the lowest-level WBS element, and do either of the following:
  • Click in the Level/Unit Name field in the row. (If displays in this field, the WBS element is dormant. You cannot add new assignments for dormant elements or any elements under it in the plan, but you can edit, delete, reassign, or reschedule existing assignments.)
  • At the end of the row, click and Add Units.
Both the Units Lookup dialog box and the Add Units dialog box display so you can select the units that you want to assign. If there is a default unit table assigned to the lowest-level WBS element of the project in the Projects hub, the Units Lookup dialog box automatically displays the units in the default unit table. If necessary, you can use the search field to remove the filter and see other available units.

In addition to unit assignments that you add yourself, the planning grid may also include assignments for units with no planned quantities but with JTD quantities charged to a lowest-level plan element. In most cases, Vantagepoint creates those assignments automatically when you display the plan. However, if the Add JTD Assignments option displays on the Actions bar, that indicates that some JTD assignments were not added because another user had the plan checked out. In that case, you can click Add JTD Assignments to update the plan with the missing assignments.

In each row, click the hyperlink to display quick information about a WBS element or unit assignment. Some unit assignments may display information on override rates. Override rates represent the unit table cost and/or bill rates saved on the unit assignment row at the time it was added, which are different from the current rates on the unit table assigned to the row. To replace override rates with the current rates in the unit table, select the Recalculate Planned Cost or Recalculate Planned Billing checkbox on the Units tab of the Plan Settings dialog box (Other Actions > Plan Settings).

By default, only names display for WBS elements, but you have the option to display numbers along with the names. Click > Column Settings and then select the Show Project Numbers checkbox on the Column Settings dialog box.

Click this icon to display brief descriptions of all the columns that you can select for the middle section of the grid. The columns displayed here depend on whether Cost or Billing is selected in the upper-right corner of the form.
Show Less and Show More

Use these links at the top of the Level/Unit Name column to hide or show the columns you have selected for display in the middle section of the grid. Hiding those columns provides space to display more calendar period columns.

If the columns are visible, click Show Less to hide them. The link then changes to Show More. Click that link to display the columns again.

You can pin individual columns if you want them to display even when you click Show Less. To do that, click > Column Settings and then select for those columns on the Column Settings dialog box.

To add unit assignments for a WBS element, check out the plan, hover over the WBS row, and click in the Level/Unit Name field to display the Units Lookup and the Add Units dialog boxes to select the units.

If displays in this field, the WBS element is dormant. You cannot add new assignments for dormant elements or any elements under it in the plan structure, but you can edit, delete, reassign, or reschedule existing assignments.

Contents: Middle Grid Section - Billing View Columns

Click > Column Settings to select the columns that you want to display in this section of the grid in Billing View. You may be able to select any of the columns described below, or you may have only a subset of them available to you, depending on the settings selected on the Grids form (Settings > Resource Planning > Grids).

If you use multiple currencies and the project is set up to use a billing currency that is different from the project currency, the Use Billing (Not Project) Currency for Reporting option in Settings > Accounting > Labor Options determines whether or not the amounts in Billing View display in the billing currency. Otherwise, the amounts are displayed in the project currency.

The JTD date in this grid is defined by the Job-to-Date (JTD) Through setting in Settings > Resource Planning > Plan Settings. The setting determines the date for calculating the unit JTD (posted transactions) and then uses the next day and beyond to calculate the estimate-to-complete (ETC) date.

As you make entries in calendar period columns, columns in this middle section of the grid that contain calculated values based on the calendar period entries, such as planned billing amounts, are not updated immediately. Instead, Vantagepoint displays those values with a strikethrough to indicate that they are no longer current. When you move to another grid row or, with a few exceptions, otherwise move off the current row, all grid cells with out-of-date values are automatically recalculated, and the strikethrough is removed.

Field Description
Account For a unit row, this column displays the account associated with the unit when it was added to the plan or when it was reassigned.

For a WBS row, this column is blank.

Account Type For a unit row, this column displays the account type (for example, Direct or Reimbursable Expense) of the account associated with the unit when it was added to the plan or when it was reassigned.

For a WBS row, this column is blank.

Assignment Start For a unit row, this column displays the start date for that unit's assignment. You can change this date for a unit row.

For a WBS row, this column displays the start date for the earliest unit assignment for that WBS element.

If you change this date or click and then Reschedule, the Reschedule Unit Assignments dialog box displays so you can specify if you want to preserve the same number of days between the assignment start and end dates or change the duration of the assignment date range.

If you change this date in a way that places any part of the assignment date range outside of the plan date range for the parent WBS element, Vantagepoint notifies you that it will also adjust the plan dates to include the complete assignment date range.

Assignment End For a unit row, this column displays the end date for that unit's assignment. You can change this date for a unit row.

For a WBS row, this column displays the end date for the latest unit assignment for that WBS element.

If you change this date or click and then Reschedule, the Reschedule Unit Assignments dialog box displays so you can specify if you want to preserve the same number of days between the assignment start and end dates or change the duration of the assignment date range.

If you change this date in a way that places any part of the assignment date range outside of the plan date range for the parent WBS element, Vantagepoint notifies you that it will also adjust the plan dates to include the complete assignment date range.

Baseline Billing For a unit row, this column displays the total billing amount that is saved in the baseline.

For a WBS row, this column displays the sum of the unit assignment baseline billing amounts for that WBS element.

The baseline acts as a snapshot of the plan at a certain point in time. To save a baseline, click Save Baseline on the Actions bar. You can have only one baseline version for any plan. Changes you make to the existing baseline overwrite the previous baseline data. You can change the baseline only if your role has appropriate access rights.

Baseline Quantity For a unit row, this column displays the total quantity that is saved in the baseline.

For a WBS row, this column displays the sum of the unit assignment baseline quantities for that WBS element.

The baseline acts as a snapshot of the plan at a certain point in time. To save a baseline, click Save Baseline on the Actions bar. You can have only one baseline version for any plan. Changes you make to the existing baseline overwrite the previous baseline data. You can change the baseline only if your role has appropriate access rights.

Calculated % Complete Billing For a unit row, this column displays the percent complete based on billing amounts as of the JTD date.

For a WBS row, this column displays the overall percent complete for that WBS element's unit assignments based on billing amounts, as of the JTD date.

Calculation: (JTD billing amount / EAC billing amount) x 100

Contract For a WBS row, this column displays the sum of all the unit contract amounts on the Contract tab of the Plan form for that WBS element.

For a unit row, this column is blank.

Contract Less EAC Billing

For a WBS row, this column displays the difference between the unit contract amount and the overall estimate-at-completion (EAC) billing amount for that WBS element's unit assignments as of the JTD date. Negative amounts display in red.

Calculation: Unit contract amount - EAC billing amount

For a unit row, this column is blank.

Contract Less JTD Billing

For a WBS row, this column displays the difference between the unit contract amount and the sum of the units billing amount for posted transactions as of the JTD date for that WBS element. Negative amounts display in red.

Calculation: Unit contract amount - JTD billing amount

For a unit row, this column is blank.

EAC Billing For a unit row, this column displays the estimate-at-completion (EAC) billing amount.

For a WBS row, this column displays the sum of the EAC amounts for that WBS element's unit assignments.

Calculation: JTD billing amount as of the JTD date + ETC billing amount from the day after the JTD date forward

EAC Quantity For a unit row, this column displays the EAC quantity through the JTD date.

For a WBS row, this column displays the sum of the EAC quantities for that WBS element's unit assignments.

Calculation: JTD quantity as of the JTD date + ETC quantity from the day after JTD date forward

ETC Billing For a unit row, this column displays the estimate-to-complete (ETC) billing amount. This is the planned amount remaining for that assignment from the day after the JTD date through the end of the assignment.

For a WBS row, this column displays the sum of the ETC billing amounts for that WBS element's unit assignments.

ETC Quantity For a unit row, this column displays the total ETC quantity for that unit assignment. This is the planned quantity remaining for that assignment from the day after the JTD date through the end of the assignment.

For a WBS row, this column displays the sum of ETC quantities for that WBS element's unit assignments.

You can enter a quantity in this column for individual unit assignments. When you enter a quantity, Vantagepoint allocates the quantity to the future calendar periods for that unit assignment. Display the Planned Quantity sub-row ( > Sub-Row Selection) in the right section of the grid to see how quantities are allocated to the appropriate calendar periods.

  • If the unit assignment currently has no ETC quantities, the quantity is allocated to each calendar period in proportion to the number of work days remaining for it.
  • If the unit assignment currently has ETC quantities, the quantity you enter is allocated to each calendar period in proportion to its current ETC quantity.

    Calendar periods that currently have no ETC quantity receive no allocation.

The quantities that display in the calendar periods depend on your selection in Scale. If you later change the scale of the calendar period (for example, from Weeks to Months), Vantagepoint reallocates the quantity for the new scale.

If the assignment date range for the unit assignment includes no more work days that are later than the JTD date, you cannot enter a quantity in this field.

Because units can have different types of quantities (for example, a unit can cover the hours for a two-person survey crew and the use of equipment at a specified bill rate per hour on a project), you cannot enter aggregate planned quantities for WBS elements and have Vantagepoint allocate them to lower-level WBS elements and to individual unit assignments.

Has Predecessor This column displays a checkmark if the WBS level has at least one predecessor.
Has Successor This column displays a checkmark if the WBS level has at least one successor.
JTD <JTD Date> Billing For a unit row, this column displays the posted billing amounts through the JTD date. The JTD date displays as part of the column heading.

For a WBS row, this column displays the sum of the JTD billing amounts for that WBS element's unit assignments.

If this amount for either a WBS element or unit exceeds the planned amount, a red arrow displays next to the amount to call your attention to it.

Calculation: Sum of JTD posted amounts, at billing

JTD <JTD Date> Quantity For a unit row, this column displays the unit quantity on posted transactions through the JTD date. The JTD date displays as part of the column heading.

For a WBS row, this column displays the sum of the JTD quantities for that WBS element's unit assignments.

If this quantity for either a WBS element or a unit exceeds the planned quantity, a red arrow displays next to the quantity to call your attention to it.

Calculation: Sum of JTD posted unit quantities

Notes If the icon displays in this column for a WBS element, click that icon to review or edit the existing notes for that element.

If the icon does not display for a WBS element, hover over the row and click to add a note for that element.

A note entered on this tab is also available in the Notes column on all the other planning tabs on the Plan form. The plan notes for a WBS element are also displayed in an info bubble, along with other information for that element, when you click on the WBS element in any of the planning grids in the Projects hub or in Resource Management.

This option is not available for assignment rows.

Organization If Vantagepoint is set up to use organizations, this column displays the organization with which each WBS element is associated. For an assignment row, this column is blank.
Plan Start For a WBS row, this column displays the plan start date for that WBS element. For an assignment row, this column is blank.

Vantagepoint provides default plan dates when it creates the plan initially (for more information, see Default Plan Dates for New Projects). Review those default dates and change any that are not correct. When you enter a plan date on this tab, the corresponding plan dates on the other planning tabs are also updated.

If you change this date or click and then Reschedule, the Reschedule Plan Dates dialog box displays so you can specify if you want to preserve the same number of days between the plan start and end dates or change the duration of the plan date range.

If you select a date that is earlier than the plan start date for any higher-level WBS elements in the same branch, those plan start dates are adjusted accordingly. When you change plan dates, Vantagepoint checks for established schedule dependencies and notifies you when adjustments to plan dates impact these relationships.

Plan End For a WBS row, this column displays the plan end date for the WBS element. For an assignment row, this column is blank.

Vantagepoint provides default plan dates when it creates the plan initially (for more information, see Default Plan Dates for New Projects). Review those default dates and change any that are not correct. When you enter a plan date on this tab, the corresponding plan dates on the other planning tabs are also updated.

If you change this date or click and then Reschedule, the Reschedule Plan Dates dialog box displays so you can specify if you want to preserve the same number of days between the plan start and end dates or change the duration of the plan date range.

If you select a date that is later than the plan end date for any higher-level WBS elements in the same branch, those plan end dates are adjusted accordingly. When you change plan dates, Vantagepoint checks for established schedule dependencies and notifies you when adjustments to plan dates impact these relationships.

Planned Billing

For a unit row, this column displays the planned billing amount for the assignment's planned unit quantities (past and ETC).

Calculation for a unit row: (Planned unit quantity x Unit billing rate) x Unit billing multiplier

For a WBS row, this column displays the sum of planned billing amounts for that WBS element's unit assignments. If this amount does not match the contract amount for the WBS element, a blue arrow displays next to the quantity to call your attention to it.

Calculation for a WBS row: Sum of planned billing amounts on each unit row

Planned Less EAC Billing

For a unit row, this column displays the difference, at billing, between the planned amount and the EAC amount as of the JTD date.

For a WBS row, this column displays the difference between the sum of the planned billing amounts and the sum of the EAC billing amounts for that WBS element's unit assignments.

Calculation: Planned billing amount - EAC billing amount

Planned Less EAC Quantity For a unit row, this column displays the difference between the planned quantity and the EAC quantity as of the JTD date.

For a WBS row, this column displays the difference between the sum of the planned quantities and the sum of the EAC quantities for that WBS element's unit assignments.

Calculation: Planned quantity - EAC quantity

Planned Less JTD Billing

For a unit row, this column displays the difference, at billing, between the planned amount and the JTD amount.

For a WBS row, this column displays the difference between the sum of the planned billing amounts and the sum of the JTD billing amounts for that WBS element's unit assignments.

Calculation: Planned billing amount - JTD billing amount

Planned Less JTD Quantity For a unit row, this column displays the difference between the planned quantity and the JTD quantity.

For a WBS row, this column displays the difference between the sum of the planned quantities and the sum of the JTD quantities for that WBS element's unit assignments.

Calculation: Planned quantity - JTD quantity

Planned Quantity For a unit row, this column displays the total planned quantity (past and ETC).

For a WBS row, this column displays the sum of planned quantities for that WBS element's unit assignments.

Project Manager This column displays the project manager for the WBS element.
Status This column displays the status of the WBS and unit rows: (Active), (Inactive), and (Dormant).
Unit Number For a unit row, this column displays the unit number.

For a WBS row, this column is blank.

Unit Table For a unit row, this column displays the unit table that applies to the unit assignment.

For a WBS row, this column is blank.

Contents: Middle Grid Section - Cost View Columns

Click > Column Settings to select the columns you want to display in this section of the grid in Cost View. You may be able to select any of the columns described below, or you may only have a subset of them available to you, depending on the settings selected on the Grids form (Settings > Resource Planning > Grids).

If you use multiple currencies and the project is set up to use a billing currency that is different than the project currency, the amounts in the Cost View always display in the project currency.

The JTD date in this grid is defined by the Job-to-Date (JTD) Through setting in Settings > Resource Planning > Plan Settings. The setting determines the date for calculating the unit JTD (posted transactions) and then uses the next day and beyond to calculate the estimate-to-complete (ETC) date.

As you make entries in calendar period columns, columns in this middle section of the grid that contain calculated values based on the calendar period entries, such as planned cost amounts, are not updated immediately. Instead, Vantagepoint displays those values with a strikethrough to indicate that they are no longer current. When you move to another grid row or, with a few exceptions, otherwise move off the current row, all grid cells with out-of-date values are automatically recalculated, and the strikethrough is removed.

Field Description
Account For a unit row, this column displays the account associated with the unit when it was added to the plan or when it was reassigned.

For a WBS row, this column is blank.

Account Type For a unit row, this column displays the account type (for example, Direct or Reimbursable Expense) of the account associated with the unit when it was added to the plan or when it was reassigned.

For a WBS row, this column is blank.

Assignment Start For a unit row, this column displays the start date for that unit's assignment. You can change this date for a unit row.

For a WBS row, this column displays the start date for the earliest unit assignment for that WBS element.

If you change this date or click and then Reschedule, the Reschedule Unit Assignments dialog box displays so you can specify if you want to preserve the same number of days between the assignment start and end dates or change the duration of the assignment date range.

If you change this date in a way that places any part of the assignment date range outside of the plan date range for the parent WBS element, Vantagepoint notifies you that it will also adjust the plan dates to include the complete assignment date range.

Assignment End For a unit row, this column displays the end date for that unit's assignment. You can change this date for a unit row.

For a WBS row, this column displays the end date for the latest unit assignment for that WBS element.

If you change this date or click and then Reschedule, the Reschedule Unit Assignments dialog box displays so you can specify if you want to preserve the same number of days between the assignment start and end dates or change the duration of the assignment date range.

If you change this date in a way that places any part of the assignment date range outside of the plan date range for the parent WBS element, Vantagepoint notifies you that it will also adjust the plan dates to include the complete assignment date range.

Baseline Cost For a unit row, this column displays the total cost amount that is saved in the baseline.

For a WBS row, this column displays the sum of the unit assignment baseline cost amounts for that WBS element.

The baseline acts as a snapshot of the plan at a certain point in time. To save a baseline, click Save Baseline on the Actions bar. You can have only one baseline version for any plan. Changes you make to the existing baseline overwrite the previous baseline data. You can change the baseline only if your role has appropriate access rights.

Baseline Quantity For a unit row, this column displays the total quantity that is saved in the baseline.

For a WBS row, this column displays the sum of the unit assignment baseline quantities for that WBS element.

The baseline acts as a snapshot of the plan at a certain point in time. To save a baseline, click Save Baseline on the Actions bar. You can have only one baseline version for any plan. Changes you make to the existing baseline overwrite the previous baseline data. You can change the baseline only if your role has appropriate access rights.

Calculated % Complete Cost For a unit row, this column displays the percent complete based on cost amounts as of the JTD date.

For a WBS row, this column displays the overall percent complete for that WBS element's unit assignments based on cost amounts, as of the JTD date.

Calculation: (JTD cost amount / EAC cost amount) x 100

Contract For a WBS row, this column displays the sum of all the unit contract amounts on the Contract tab of the Plan form for that WBS element.

For a unit row, this column is blank.

Contract Less EAC Cost

For a WBS row, this column displays the difference between the unit contract amount and the overall estimate-at-completion (EAC) cost amount for that WBS element's unit assignments as of the JTD date. Negative amounts display in red.

Calculation: Unit contract amount - EAC cost amount

For a unit row, this column is blank.

Contract Less JTD Cost

For a WBS row, this column displays the difference between the unit contract amount and the sum of the units cost amount for posted transactions as of the JTD date for that WBS element. Negative amounts display in red.

Calculation: Unit contract amount - JTD cost amount

For a unit row, this column is blank.

EAC Cost For a unit row, this column displays the estimate-at-completion (EAC) cost amount.

For a WBS row, this column displays the sum of the EAC cost amounts for that WBS element's unit assignments.

Calculation: JTD cost amount as of the JTD date + ETC cost amount from the day after the JTD date forward

EAC Quantity For a unit row, this column displays the EAC quantity through the JTD date.

For a WBS row, this column displays the sum of the EAC quantities for that WBS element's unit assignments.

Calculation: JTD quantity as of the JTD date + ETC quantity from the day after JTD date forward

ETC Cost For a unit row, this column displays the estimate-to-complete (ETC) cost amount. This is the planned amount remaining for that assignment from the day after the JTD date through the end of the plan.

For a WBS row, this column displays the sum of the ETC cost amounts for that WBS element's unit assignments.

ETC Quantity For a unit row, this column displays the total ETC quantity for that unit assignment. This is the planned quantity remaining for that assignment from the day after the JTD date through the end of the assignment.

For a WBS row, this column displays the sum of ETC quantities for that WBS element's unit assignments.

You can enter a quantity in this column for individual unit assignments. When you enter a quantity, Vantagepoint allocates the quantity to the future calendar periods for that unit assignment. Display the Planned Quantity sub-row ( > Sub-Row Selection) in the right section of the grid to see how quantities are allocated to the appropriate calendar periods.

  • If the unit assignment currently has no ETC quantities, the quantity is allocated to each calendar period in proportion to the number of work days remaining for it.
  • If the unit assignment currently has ETC quantities, the quantity you enter is allocated to each calendar period in proportion to its current ETC quantity.

    Calendar periods that currently have no ETC quantity receive no allocation.

The quantities that display in the calendar periods depend on your selection in Scale. If you later change the scale of the calendar period (for example, from Weeks to Months), Vantagepoint reallocates the quantity for the new scale.

If the assignment date range for the unit assignment includes no more work days that are later than the JTD date, you cannot enter a quantity in this field.

Because units can have different types of quantities (for example, a unit can cover the hours for a two-person survey crew and the use of equipment at a specified bill rate per hour on a project), you cannot enter aggregate planned quantities for WBS elements and have Vantagepoint allocate them to lower-level WBS elements and to individual unit assignments.

JTD <JTD Date> Cost For a unit row, this column displays the posted cost amounts through the JTD date. The JTD date displays as part of the column heading.

For a WBS row, this column displays the sum of JTD cost amounts for that WBS element's unit assignments.

If this amount for either a WBS element or a unit assignment exceeds the planned amount, a red arrow displays next to the amount to call your attention to it.

Calculation: Sum of JTD posted amounts, at cost

JTD <JTD Date> Quantity For a unit row, this column displays the unit quantity on posted transactions through the JTD date. The JTD date displays as part of the column heading.

For a WBS row, this column displays the sum of the JTD quantities for that WBS element's unit assignments.

If this quantity for either a WBS element or a unit exceeds the planned quantity, a red arrow displays next to the quantity to call your attention to it.

Calculation: Sum of JTD posted unit quantities

Notes If the icon displays in this column for a WBS element, click that icon to review or edit the existing notes for that element.

If the icon does not display for a WBS element, hover over the row and click to add a note for that element.

A note entered on this tab is also available in the Notes column on all the other planning tabs on the Plan form. The plan notes for a WBS element are also displayed in an info bubble, along with other information for that element, when you click on the WBS element in any of the planning grids in the Projects hub or in Resource Management.

This option is not available for assignment rows.

Organization If Vantagepoint is set up to use organizations, this column displays the organization with which each WBS element is associated. For an assignment row, this column is blank.
Plan Start For a WBS row, this column displays the plan start date for that WBS element. For an assignment row, this column is blank.

Vantagepoint provides default plan dates when it creates the plan initially (for more information, see Default Plan Dates for New Projects). Review those default dates and change any that are not correct. When you enter a plan date on this tab, the corresponding plan dates on the other planning tabs are also updated.

If you change this date or click and then Reschedule, the Reschedule Plan Dates dialog box displays so you can specify if you want to preserve the same number of days between the plan start and end dates or change the duration of the plan date range.

If you select a date that is earlier than the plan start date for any higher-level WBS elements in the same branch, those plan start dates are adjusted accordingly. When you change plan dates, Vantagepoint checks for established schedule dependencies and notifies you when adjustments to plan dates impact these relationships.

Plan End For a WBS row, this column displays the plan end date for the WBS element. For an assignment row, this column is blank.

Vantagepoint provides default plan dates when it creates the plan initially (for more information, see Default Plan Dates for New Projects). Review those default dates and change any that are not correct. When you enter a plan date on this tab, the corresponding plan dates on the other planning tabs are also updated.

If you change this date or click and then Reschedule, the Reschedule Plan Dates dialog box displays so you can specify if you want to preserve the same number of days between the plan start and end dates or change the duration of the plan date range.

If you select a date that is later than the plan end date for any higher-level WBS elements in the same branch, those plan end dates are adjusted accordingly. When you change plan dates, Vantagepoint checks for established schedule dependencies and notifies you when adjustments to plan dates impact these relationships.

Planned Cost

For a unit row, this column displays the planned cost amount for the assignment's planned unit quantities (past and ETC).

Calculation for a unit row: Planned quantity x Unit cost rate

For a WBS row, this column displays the sum of planned cost amounts for that WBS element's unit assignments. If this amount does not match the contract amount for the WBS element, a blue arrow displays next to the quantity to call your attention to it.

Calculation for a WBS row: Sum of planned cost amounts on each unit row

Planned Less EAC Cost

For a unit row, this column displays the difference, at cost, between the planned amount and the EAC amount as of the JTD date.

For a WBS row, this column displays the difference between the sum of the planned cost amounts and the sum of the EAC cost amounts for that WBS element's unit assignments.

Calculation: Planned cost amount - EAC cost amount

Planned Less EAC Quantity For a unit row, this column displays the difference between the planned quantity and the EAC quantity as of the JTD date.

For a WBS row, this column displays the difference between the sum of the planned quantities and the sum of the EAC quantities for that WBS element's unit assignments.

Calculation: Planned quantity - EAC quantity

Planned Less JTD Cost

For a unit row, this column displays the difference, at cost, between the planned amount and the JTD amount.

For a WBS row, this column displays the difference between the sum of the planned cost amounts and the sum of the JTD cost amounts for that WBS element's unit assignments.

Calculation: Planned cost amount - JTD cost amount

Planned Less JTD Quantity For a unit row, this column displays the difference between the planned quantity and the JTD quantity.

For a WBS row, this column displays the difference between the sum of the planned quantities and the sum of the JTD quantities for that WBS element's unit assignments.

Calculation: Planned quantity - JTD quantity

Planned Quantity For a unit row, this column displays the total planned quantity (past and ETC).

For a WBS row, this column displays the sum of planned quantities for that WBS element's unit assignments.

Project Manager This column displays the project manager for the WBS element.
Status This column displays the status of the WBS and unit rows: (Active), (Inactive), and (Dormant).
Unit Number For a unit row, this column displays the unit number.

For a WBS row, this column is blank.

Unit Table For a unit row, this column displays the unit table that applies to the unit assignment.

For a WBS row, this column is blank.

Contents: Right Grid Section

The right grid section displays actual, baseline, and planned unit data by calendar period for the selected project. On the Sub-Row Selection dialog box ( > Sub-Row Selection), select at least one sub-row to display in this section of the grid.

Field Description
Calendar period columns

Use the calendar period columns to view actual, baseline, and planned unit data. Your selection in Scale determines whether each calendar period column represents a day, week, or month. The number of calendar period columns depends on the scale you select and on the plan start and end dates. If you select to display actual and/or baseline sub-rows and there are corresponding values outside of the plan date range, additional calendar period columns display to represent those amounts. Use the arrows in the date range selector above the grid to load earlier or later sets of periods.

Because quantities for a WBS row could represent a mix of different types of units, you can only enter quantities in unit rows. To enter planned quantities for the unit from the day after the JTD date through the end of the assignment, do any of the following:
  • Use the ETC Quantity field in the middle section of the grid. When you enter a quantity, Vantagepoint allocates the quantity to the future calendar periods for that unit assignment.
  • To directly enter ETC quantities in the calendar periods, display the Planned Quantity sub-row in the right section of the grid.

You can enter quantities for calendar periods that are outside of the unit's current assignment date range, as long as the periods are still within the specified plan dates on the top WBS element row. In that case, Vantagepoint adjusts the assignment dates to include that calendar period. If that calendar period currently has a quantity for the unit assignment, the quantity you enter is allocated to days in proportion to each day's current quantity. If the calendar period has no quantity for the unit assignment, the quantity you enter is allocated equally to each work day in the calendar period.

If you enter unit quantities in calendar periods before or after the current plan dates and there are schedule dependencies established between WBS elements in your project, Vantagepoint determines if the change affects the relationships and notifies you before updating the schedule.

If a calendar period date range includes some dates that are on or before the JTD date and some dates that are after, you can enter ETC quantities for that calendar period. To do that, click the calendar period column on a unit row to display fields that show both the quantity for past days in the period and the current ETC quantity. You can enter or change the ETC quantity. The grid cell then displays the updated sum of the past quantity and ETC quantity.

As you make entries in calendar period columns, columns in the middle section of the grid that contain calculated values based on the calendar period entries, such as planned cost and billing amounts, are not updated immediately. Instead, Vantagepoint displays those values with a strikethrough to indicate that they are no longer current. When you move to another grid row or, with a few exceptions, otherwise move off the current row, all grid cells with out-of-date values are automatically recalculated, and the strikethrough is removed.

When Vantagepoint updates all values after you have entered changes to some calendar periods and moved off the row, you may see minor changes in the quantities for other calendar periods that you did not edit. This occurs when the scale at which you make your changes is smaller than the scale at which the quantities were previously saved (for example, if they were previously saved in monthly periods, and you change the quantity for a weekly period). That, in turn, can change the quantity to be allocated and/or the number of periods over which they are allocated, resulting in small differences for individual calendar periods.

Planned Quantity For a WBS row, this sub-row displays a portion of the total planned quantity (past and ETC) for that WBS element's unit assignments in each calendar period.

For a unit row, this sub-row displays the planned quantity that is allocated to each calendar period. This is the only editable sub-row in the calendar section of the unit planning grid. You can enter planned quantities from the day after the JTD date through the end of the assignment or plan, if the plan end date is beyond the assignment end date. When you enter quantities up to the plan end date, Vantagepoint extends the assignment end date on the unit row and the plan end date on any higher-level WBS element in the same branch.

Planned Cost For a WBS row, this sub-row displays a portion of the total planned cost amounts for that WBS element's unit assignments in each calendar period.

For a unit row, this sub-row displays the planned cost amount for that assignment's planned quantities (past and ETC) in each calendar period.

You can display this sub-row regardless of the specified budget type for the plan. If you set the Budget Type option to Billing on the Plan Settings dialog box, this sub-row will not display any values.

Planned Billing For a WBS row, this sub-row displays a portion of the total planned billing amount for that WBS element's unit assignments in each calendar period.

For a unit row, this sub-row displays the planned billing amount for that assignment's planned quantities (past and ETC) in each calendar period.

You can display this sub-row regardless of the specified budget type for the plan. If you set the Budget Type option to Cost on the Plan Settings dialog box, this sub-row will not display any values.

Actual Quantity

For a WBS or unit row, this sub-row displays the unit quantity on posted transactions through the JTD date in each calendar period.

If you display this sub-row and there are actual and/or baseline values that are outside of the plan date range, Vantagepoint displays additional calendar period columns to represent those amounts.

Actual Cost

For a WBS or unit row, this sub-row displays the posted cost amounts through the JTD date in each calendar period.

If you display this sub-row and there are actual and/or baseline values that are outside of the plan date range, Vantagepoint displays additional calendar period columns to represent those amounts.

You can display this sub-row regardless of the specified budget type for the plan. If you set the Budget Type option to Billing on the Plan Settings dialog box, this sub-row will not display any values.

Actual Billing

For a WBS or unit row, this sub-row displays the posted billing amounts through the JTD date in each calendar period.

If you display this sub-row and there are actual and/or baseline values that are outside of the plan date range, Vantagepoint displays additional calendar period columns to represent those amounts.

You can display this sub-row regardless of the specified budget type for the plan. If you set the Budget Type option to Cost on the Plan Settings dialog box, this sub-row will not display any values.

Baseline Quantity

For a WBS or unit row, this sub-row displays the quantity that is saved in the baseline in each calendar period.

If you display this sub-row and there are actual and/or baseline values that are outside of the plan date range, Vantagepoint displays additional calendar period columns to represent those amounts.

Baseline Cost

For a WBS or unit row, this sub-row displays the cost amount that is saved in the baseline in each calendar period.

If you display this sub-row and there are actual and/or baseline values that are outside of the plan date range, Vantagepoint displays additional calendar period columns to represent those amounts.

You can display this sub-row regardless of the specified budget type for the plan. If you set the Budget Type option to Billing on the Plan Settings dialog box, this sub-row will not display any values.

Baseline Billing

For a WBS or unit row, this sub-row displays the billing amount that is saved in the baseline in each calendar period.

If you display this sub-row and there are actual and/or baseline values that are outside of the plan date range, Vantagepoint displays additional calendar period columns to represent those amounts.

You can display this sub-row regardless of the specified budget type for the plan. If you set the Budget Type option to Cost on the Plan Settings dialog box, this sub-row will not display any values.

This icon displays at the end of the row when you click or hover over a grid row. These actions are enabled when the plan is checked out. Click the icon to select one of these actions for that row:
  • Add Units: This option is available only when you select at the lowest-level element of the plan WBS. Click this option to display the Units Lookup and Add Units dialog boxes, on which you can assign units to the selected WBS element.
  • Reschedule: To change plan date ranges, click this option on a WBS row. To change unit assignment date ranges, click this option on a unit row. In either case, you can also indicate how to distribute the planned quantities within the new schedule.
  • Reassign: On a unit row, click this option to transfer all or part of the planned unit quantities to another unit or account.
  • Delete: Click this option to delete the unit assignment. If the assignment has JTD quantities or has been saved as part of the baseline plan, you cannot delete the assignment. In those cases, however, you can still use this option to delete all planned quantities for the assignment.