To have
Vantagepoint allocate summary planned hours to a resource's individual assignments, display the resource in the Resource View grid and enter the summary hours in the appropriate field and at the appropriate level of the plan work breakdown structure (WBS).
To enter and allocate summary planned hours for a resource:
-
In the Navigation pane, select
.
-
If necessary, use a search to display, in the grid, the resource for whom you want to enter summary hours.
-
If
Show Capacity above the right corner of the grid is not set to
Planned Hours, select that option.
-
Expand the plan structure to display the WBS element for which you which you want to enter summary hours.
-
Click the row to display the entry fields.
-
Do one of the following:
- To allocate summary ETC hours over the assignment date range for the WBS element, enter the hours in
Total ETC Hours.
- To allocate summary ETC hours over the current forecast range, set the forecast range correctly and then enter the hours in
Range ETC Hours.
- To allocate summary ETC hours over the portion of the assignment date range that precedes the start date of the current forecast range, set the forecast range correctly and then enter the hours in
ETC Before.
- To allocate summary ETC hours over the portion of the assignment date range that follows the end date of the current forecast range, set the forecast range correctly and enter the hours in
ETC After.
Before entering summary hours in
Range ETC Hours,
ETC Before, or
ETC After, make sure the forecast range is set correctly.
Vantagepoint allocates the hours to calendar periods for that WBS row. If you enter summary hours for a WBS row for which lower-level rows are displayed, it also allocates the hours to calendar periods for each lower-level row.