Milestone Field Descriptions

The fields (columns) in the Milestone sheet provide information about the milestones. MPM displays <Required> in fields that are required. You can display or hide the fields using the Column Hide command on the Format menu.

Most of the WBS fields can be displayed in the Baseline view. However, they cannot be edited and initially they are hidden in the view. For a description of the fields, see WBS Field Descriptions.

The important fields are described on the pages that follow. They are listed in the order they display in the window. To jump to a specific field description, select the field name from the list that follows. You can also scroll through the topic.

Level

Symbol

WBS ID

Complete

Milestone ID

% Complete

Description

Cum BCWP

EVM

Baseline Start

BCWP Base

Baseline Complete

Schedule Date

Last Statused Date

Forecast Date

Base WBS

Weight

 

If you delete an EVM from a WBS element, MPM removes all milestones from the WBS. If you assign an EVM to a WBS element that does not currently have any milestones, MPM adds default Start and Complete milestones to the WBS. You can accept, edit, or delete these default milestones.

Total Dollars is the default value.

The BCWP Base unit should match the Baseline Estimate Type you selected in the Integrated Planning window. For example, if the estimates are being recorded as Hours, then the BCWP Base unit should also be Hours.

If you change the Schedule Date and the Forecast Date for the milestone is blank, MPM changes the Forecast Date to match the Schedule Date.

For EVMs other than No EVM Required, Level of Effort (LOE), Key Event, and Apportioned, when you update the field, MPM updates the milestone's % Complete field appropriately and calculates a new percent complete and cum BCWP for the WBS.

On a WBS row, the % Complete field shows the cumulative percent complete for a WBS element if the WBS element has an EVM assigned other than No EVM Required. N/A (Not Applicable) will display for WBS elements that use an EVM of Level of Effort or Key Event.

On a milestone row, if the milestone is checked as complete, the % Complete field will display 100%. If an EVM of Milestone Weights with % Complete is used, this field holds the current percent complete value for each milestone up to 100% and will accept up to three characters of input. If you set the % Complete field to 100%, MPM will place a check mark in the Complete field. If you set the % Complete field to less than 100%, MPM will remove the check mark from the Complete field. If you update this field, MPM will calculate a new percent complete and cum BCWP for the WBS.

The % Complete value displayed is the most recent non-zero month of status, not necessarily the latest percent complete. For example, assume the % Complete values after statusing several months are: Jan 10%, Feb 20%, Mar 10%, and Apr 0%. The percent complete displayed would be March's 10%.

If a WBS element has been assigned an EVM of BCWP Entry or Earned Standards, you must enter a value in this field to status the element. For an EVM of BCWP Entry, updating the Cum BCWP will cause MPM to calculate a new percent complete for the WBS element. For an EVM of Earned Standards, updating the field will cause MPM to calculate a new percent complete for the WBS element, then apply that percent to the BAC of Hours to calculate a new cum BCWP for the WBS in Hours.

You cannot use any of the following as the Base WBS ID:

Other Fields

Most of the WBS fields can be displayed in the Milestone sheet. However, they cannot be edited and initially they are hidden in the view. For a description of the fields, see WBS Field Descriptions.