Most of the fields in the Baseline display are read-only, with the information pulled from other areas of MPM. The editable fields are:
|
|
|
|
|
|
|
To edit a resource estimate, complete the following steps:
Select the field you want to edit.
Make the change. When you change a field value, MPM changes the color of the resource estimate field text to blue indicating the estimate has been changed but not saved.
To save the change, do one of the following:
Click on another row in the window.
Click Save
Click File » Save
Press Ctrl+S
You may be prompted to confirm the save and asked if you want to save the changes to the ETC. For information on the Save options, see Saving Estimates.
If you do not want to save the changes, press Esc.
Other editing functions are covered in the following topics: