SyncProjectAndCalendarStatus Enumeration |
Specifies whether the status date of the project or TODATE period in the calendar will be synchronize when advancing the calendar of a selected project.
Namespace: Cobra.Model.WebServiceAssembly: Cobra.Model.WebService (in Cobra.Model.WebService.dll) Version: 8.5.700.3359 (8.5.0700.3359)
Syntax public enum SyncProjectAndCalendarStatus
Members Member name | Value | Description |
---|
SyncProjectWithCalendarStatus | 0 |
If the calendar set 18 contains a TODATE label, the status date of the project will be updated to match the date in the TODATE calendar entry.
|
SyncCalendarWithProjectStatus | 1 |
The TODATE period in the calendar will be updated to match the status date of the project.
|