Click or drag to resize

IntegrateActualCostsServiceArgumentsUseStatusDateAsTheActualStartDate Property

Determines whether to enable Cobra to automatically set the status of planned control accounts and work packages to In-Progress during the load actual process. Optional. If configuration file is used and this is not set, the setting in the saved configuration is used. If configuration file is not used and this is not set, the setting in the project preference is used.

Namespace:  Cobra.WebService.ClientAPI.Application.Files
Assembly:  Cobra.WebService.ClientAPI (in Cobra.WebService.ClientAPI.dll) Version: 8.4.717.3176 (8.4.0717.3176)
Syntax
C#
public Nullable<bool> UseStatusDateAsTheActualStartDate { get; set; }

Property Value

Type: NullableBoolean
See Also