Project Selection Page of the Advance Calendar Wizard

Use this page to select the project whose calendar you want to advance.

The Advance Calendar feature is used to advance the project status date to the next period in the calendar. If you have a rolling wave calendar assigned to a project, advancing the calendar will also collapse past periods and expand future periods.

Contents

Field Description
Project Enter, or use to select, a project.

Click Next to go to the next page of the wizard. If you select a master project containing one or more sub-projects whose status dates are not synchronized with the master project's status date, clicking Next displays the Synchronize Status page instead of the Periods page.