Deleting a resource
You can also delete a labor resource from Schedule Manager if it has no budget, percent distribution, task, notes, or start and end dates assigned to it.
- If you are not already working
with the project, open it by clicking it in the project list at the top
of the Project Command Center.
- Click the Manage
tab.
- Click the resource that
you want to delete, and click the Delete
button.
- Click Yes
to delete the resource. If it is a labor resource, it is deleted both from the Manage tab of the Project Command Center and from Schedule Manager.
See also
Working with the project
tree
Deleting an employee from a project
|
|