Edit a Relationship (Network)

Use this procedure to edit a relationship in a network view.

To edit a relationship in a network view:

  1. In the Project Views folder of Open Plan Explorer, select a project to display in network view.
  2. Display the Edit Relationship dialog box by doing one of the following:
    • Double-click the relationship line you want to edit.
    • Right-click the relationship line you want to edit, and click Edit Relationship on the shortcut menu.
  3. On the Edit Relationship dialog box, enter the new information about the relationship.
  4. Click OK.
    Note: You can also add, edit, and delete data for predecessors and successors directly in a cell of any activity-based spreadsheets. The Activity Predecessors and Activity Successors columns display the predecessor/successor ID, relationship type, and lag of the relationship (which is optional and may be negative) in each cell using the format <Predecessor/Successor ID><space><relationship type><+/-Lag>. For example, 1.02 SF+3d.

Related Topic