Edit a Relationship (Barchart)
Use this procedure to edit a relationship in the barchart view.
To edit a relationship from a barchart view:
- In the Project Views folder of Open Plan Explorer, select a project to display in barchart view.
- Ensure that you are in relationship mode.
- Position the cursor over the relationship line at either end of the line.
- When the cursor changes to a cross-hair, right-click the relationship line.
- On the shortcut menu, click Edit Relationship.
- In the Edit Relationship dialog box, enter the new information about the relationship.
- Click OK.
Note: You can also add, edit, and delete data for predecessors and successors directly in a cell of any activity-based spreadsheets. The
Activity Predecessors and
Activity Successors columns display the predecessor/successor ID, relationship type, and lag of the relationship (which is optional and may be negative) in each cell using the format
<Predecessor/Successor ID><space><relationship type><+/-Lag>. For example,
1.02 SF+3d.