Defining an Activity as Effort-Driven

Use this procedure to define an activity as effort-driven.

To define an activity as effort-driven:

  1. Take one of the following actions to display the Activity Details dialog box:
    • Double-click the appropriate activity.
    • Right-click the appropriate activity, and click Edit Activity on the shortcut menu.
    • Select the appropriate activity, and click Details in the Dialogs menu group of the Edit tab.
  2. From the Type list on the General tab, select Effort Driven.
  3. Click Apply.
  4. When Open Plan asks you to confirm the operation, click OK.