Defining an Activity as Effort-Driven
Use this procedure to define an activity as effort-driven.
To define an activity as effort-driven:
-
Take one of the following actions to display the Activity Details dialog box:
- Double-click the appropriate activity.
- Right-click the appropriate activity, and click Edit Activity on the shortcut menu.
- Select the appropriate activity, and click Details in the Dialogs menu group of the Edit tab.
- From the Type list on the General tab, select Effort Driven.
- Click Apply.
- When Open Plan asks you to confirm the operation, click OK.