Review Baseline Changes Dialog Box
After you make changes in the Update Baseline dialog box, you can preview your changes before they are applied to the project.
When you click the Preview button on the Update Baseline dialog box, Open Plan runs through the updates that would be made with the options you have selected and displays this dialog box that includes activities that would be added, deleted, renamed, and updated.
You may notice that there are more activities listed than you changed. This can happen when a change to one activity affects a related activity. For example, if you change the duration of Activity A, and that change affects the start date of Activity B, Activity B displays in this dialog box as updated.