Redundancy Analysis

A redundant link occurs when, in addition to the link in question, there is a more detailed logic link between the same two activities.

For example, a link from Activity A to Activity C is made redundant by an existing link from Activity A to Activity B and another one from Activity B to Activity C.

Click Redundancy Analysis to have Open Plan analyze the entire schedule and set a flag on relationships that are redundant. After you run the process, Open Plan displays the Relationship Spreadsheet view where the Redundant Flag column indicates the redundant relationships. If needed, you can filter on this flag.

You can right-click in the view and select Redundant Logic to display the Redundant Logic dialog box. The top grid includes the redundant relationship that was identified by the analysis and the bottom grid includes the relationships that make that relationship redundant. You can click Delete to delete the relationship. You cannot edit or change relationships in this grid.

Related Topic

Redundant Logic Dialog Box