Perform Time Analysis with Current Settings
Use this procedure to perform Time Analysis with the current settings.
Note: If you wish to perform time analysis without displaying the Time Analysis dialog box, you can click
Perform Time Analysis on the Processes tab. When you perform time analysis using this method, the settings that were last set on the Time Analysis dialog box control the operation. If you have not entered a Time Now for the project, Open Plan automatically displays the Time Analysis dialog box before allowing you to proceed.
To perform time analysis:
Parent Topic: Related Procedures