Review the fields that are mentioned in
Open Plan with their values and syntax, which are useful when you are creating
a calculated field or a filter.
For example, if you want to see only
activities that have an EVT type set to
Steps, you can create
this filter: EVT=[EVTE.N].
The tables below list the fields that are mentioned in Open Plan with
their values and syntax.
Activity Logic Flag
| Value
|
Syntax
|
| None
|
[LOGI. ]
|
| Start Activity
|
[LOGI.S]
|
| Finish Activity
|
[LOGI.F]
|
| Start and Finish
Activity
|
[LOGI.SF]
|
| Isolated Activity
|
[LOGI.I]
|
Activity Status
| Value
|
Syntax
|
| Planned
|
[ACTS.0]
|
| In Progress
|
[ACTT.1]
|
| Complete
|
[ACTT.2]
|
Activity Type
| Value
|
Syntax
|
| ASAP
|
[ACTT.N]
|
| ALAP
|
[ACTT.L]
|
| Start Milestone
|
[ACTT.S]
|
| Finish Milestone
|
[ACTT.F]
|
| Discontinuous
|
[ACTT.D]
|
| Subproject
|
[ACTT.P]
|
| Hammock
|
[ACTT.H]
|
| Effort Driven
|
[ACTT.R]
|
| External Subproject
|
[ACTT.E]
|
| Foreign Project
|
[ACTT.Z]
|
| Foreign Subproject
|
[ACTT.Y]
|
| Foreign Activity
|
[ACTT.G]
|
Boolean
| Value
|
Syntax
|
| True
|
[BOOL.T]
|
| False
|
[BOOL.F]
|
Critical Flag
| Value
|
Syntax
|
| Not Critical
|
[CRIT.0]
|
| Critical
|
[CRIT.1]
|
| Most Critical
|
[CRIT.2]
|
| Controlling
Critical
|
[CRIT.3]
|
Earned Value Technique
| Value
|
Syntax
|
| Level of Effort
|
[EVTE.A]
|
| % Complete
|
[EVTE.C]
|
| 50 - 50
|
[EVTE.E]
|
| 0 - 100
|
[EVTE.F]
|
| 100 - 0
|
[EVTE.G]
|
| User Defined
Percentage
|
[EVTE.H]
|
| Planning Package
|
[EVTE.K]
|
| Resource % Complete
|
[EVTE.L]
|
| Steps
|
[EVTE.N]
|
The following Cobra EVT Types are not included in any Open Plan
calculations.
| Value
|
Syntax
|
| Milestones
|
[EVTE.B]
|
| Units Complete
|
[EVTE.D]
|
| Earned As Spent
|
[EVTE.O]
|
Probability Distribution
| Value
|
Syntax
|
| Constant
|
[DIST. ]
|
| Uniform
|
[DIST.U]
|
| Normal
|
[DIST.N]
|
| Beta
|
[DIST.B]
|
| Triangular
|
[DIST.T]
|
Progress
| Value
|
Syntax
|
| None
|
[PROG. ]
|
| Remaining Duration
|
[PROG.R]
|
| Percent Complete
|
[PROG.P]
|
| Elapsed Duration
|
[PROG.E]
|
| Complete
|
[PROG.C]
|
Project Status
| Value
|
Syntax
|
| Proposed
|
[PRJS.P]
|
| Open
|
[PRJS.O]
|
| Closed
|
[PRJS.C]
|
Relationship Type
| Value
|
Syntax
|
| Finish to Start
|
[RELT.FS]
|
| Start to Start
|
[RELT.SS]
|
| Start to Finish
|
[RELT.SF]
|
| Finish to Finish
|
[RELT.FF]
|
Resource Scheduling Type
| Value
|
Syntax
|
| Normal
|
[RSCL. ]
|
| Splittable
|
[RSCL.P]
|
| Stretchable
|
[RSCL.T]
|
| Reprofileable
|
[RSCL.R]
|
| Immediate
|
[RSCL.I]
|
Resource Class
| Value
|
Syntax
|
| Labor
|
[RESC.L]
|
| Material
|
[RESC.M]
|
| Other Direct Cost
|
[RESC.C]
|
| Subcontract
|
[RESC.S]
|
Resource Type
| Value
|
Syntax
|
| Normal
|
[REST. ]
|
| Consumable
|
[REST.C]
|
| Perishable
|
[REST.D]
|
| Pool
|
[REST.P]
|
| Skill
|
[REST.S]
|
Target Type
| Value
|
Syntax
|
| None
|
[TARG. ]
|
| Not Earlier Than
|
[TARG.NE]
|
| Not Later Than
|
[TARG.NL]
|
| On
|
[TARG.ON]
|
| Fixed
|
[TARG.FX]
|