Export CAM Estimate to Complete (ETC) Baseline Data
Use this procedure to export CAM time-phased Estimate to Complete (ETC) baseline data for each CAM listed in your Open Plan project to Excel.
It creates one XLSX file for each set of activities that is associated with a single CAM value, which usually comes from a user-defined text field or a code filed in Open Plan.
To export CAM ETC baseline data:
The exported XLSX file has the format <Project Name> <CAM Value> <Today’s Date as “ddMMMyyyy”>.xlsx (for example, CLEAN ELEC 30Sept2021.xlsx), overwriting the previous exported file. The XLSX file contains baseline activities and baseline usage records that you can edit.
The CAM Value must not contain special characters that are not allowed in a Windows file name (/ \ : * ? " < > |). If it does, Open Plan replaces them with "_".