Display the Replan Activities Dialog Box

Use this procedure to display the Replan Activities dialog box.

To display the Replan Activity dialog box

  1. In a spreadsheet view, right-click an activity that meets the following conditions:
    • It has no child activities.
    • Its status is In Progress.
    • Its Actual Start date is not blank.
    • Its Actual Finish date is blank.
    • It is not a foreign activity.
  2. On the context menu, select Replan Activity.