Auto-Analyze

Use this option to automatically calculate time analysis whenever you make a date-related change to the project.

To automatically calculate dates for new activities, select the Calculate dates even if TA is turned off? field on the Options dialog box Project tab.

Related Topic

Time Analysis Options Tab