Toggle Active State of Resources under Preparation

Use the Resources under Preparation submodule to toggle the active state of resources under preparation.

To use the Resources under Preparation submodule, you must have access to Tasks as defined in the User Access Rights submodule under Settings.

To toggle the active state of a resource under preparation:

  1. On the main toolbar, click Tasks .
  2. In the left pane of the Tasks screen, click Follow-up > Resources under Preparation.
  3. On the grid toolbar, click 10 - Under preparation .
  4. Highlight the resource under preparation that you want to toggle the active state of and click Toggle resource active state .
  5. In the confirmation dialog box, click Yes.