Use the Tasks submodule to automatically create a task for phases for which you have yet to create task.

To use the Tasks submodule, you must have access to Jobs as defined in the User Access Rights submodule under Settings.

To create a task for all phases with unassigned tasks:

  1. On the main toolbar, click Jobs .
  2. On the side toolbar of the Jobs screen, click Jobs List and highlight the job containing the phases that you want to modify.
  3. On the side toolbar of the Jobs screen, click Tasks.
  4. On the Tasks screen, click the Phases tab.
  5. On the Phases tab toolbar, click Create a Task for All Phases Where There is Not Already Assigned a Task .