Apply Phase Color to All Related Tasks (from the Phase Settings Screen)
Use the Tasks submodule to apply phase color to all related tasks.
To use Tasks, you must have access to Jobs as defined in User Access Rights under Settings.
To apply phase color to all related tasks:
-
On the main toolbar, click
Jobs
.
- In the left pane of the Jobs page, click Jobs List and highlight the job containing the phase that you want to update.
- In the left pane of the Jobs page, click Tasks.
- On the Tasks page, click the Tasks tab.
- On the grid toolbar, click the Gantt view.
-
In the grid, highlight the phase that you want to update and click
Phase Settings
on the tab toolbar.
- In the Color section of the screen, select a color that you want to be applied to the tasks within the selected phase.
- When prompted for confirmation, click Yes.
Parent Topic: Tasks Tab