Apply Phase Color to All Related Tasks (from the Phase Settings Screen)

Use the Tasks submodule to apply phase color to all related tasks.

To use the Tasks submodule, you must have access to Jobs as defined in the User Access Rights submodule under Settings.

To apply phase color to all related tasks:

  1. On the main toolbar, click Jobs .
  2. On the side toolbar of the Jobs screen, click Jobs List and highlight the job containing the phase that you want to update.
  3. On the side toolbar of the Jobs screen, click Tasks.
  4. On the Tasks screen, click the Tasks tab.
  5. On the grid toolbar, click the Gantt view.
  6. In the grid, highlight the phase that you want to update and click Phase Settings on the tab toolbar.
  7. In the Color section of the screen, select a color that you want to be applied to the tasks within the selected phase.
  8. When prompted for confirmation, click Yes.