Schedule Export Process Errors

The following are the Schedule Export process validations error messages displayed in the Process Log and the action required for the user.

Message

Action

MSP Unique ID and/or Activity ID are required when exporting activity.

Select the MSP Unique ID or the Activity ID fields in the Field Selector.

Tip: You should export the Microsoft Project Outline Number to be the activity ID. Using that number gives you the advantage of being able to outline the schedule data in PM Compass just like it is in MSP.

This only works when Primavera/Other is selected as the scheduling tool on the Projects Schedule Integration tab.

Access to the path <path provided> is denied.

Select a different path for the output file. Make sure you have full access to write in that folder.

MSP Unique ID and/or Activity ID are required when exporting resource assignments.

Select the MSP Unique ID or the Activity ID fields in the Field Selector.

Tip: You should export the Microsoft Project Outline Number to be the activity ID. Using that number gives you the advantage of being able to outline the schedule data in PM Compass just like it is in MSP.

This only works when Primavera/Other is selected as the scheduling tool on the Projects Schedule Integration tab.

No fields are selected.  The export file will be empty.

Select the fields to be exported.

No fields are selected in the Activity field picker.  The export file will be empty.

Open the Activity field picker and select the fields to export.

No fields are selected in the Resource assignment field picker.  The export file will be empty

Open the Resource assignment field picker and select the fields to export.