Work Authorization Workflow Steps

When you create a new Work Authorization, you can save it until you are ready to start the workflow steps. When you create a new Work Authorization, the ID and title are populated based on settings in the Workflow Type Configuration.

Select the project and control account to populate the dates, SOW and Details grid from the Control Account table.

Click the Start Workflow button on the form to start the workflow steps.

Step 1

Submit to the CAM to update the SOW

When you start the workflow steps, the following happens:

Log in as the CAM identified on the control account (in Cobra) for the selected control account.  

If you cancel the Work Authorization at any point during the process, the following occurs:

If you suspend the workflow steps at any point during the process, the following occurs:

The workflow process stops until a user resumes the process.  The Suspend button changes to Resume if the Work Authorization has been suspended.  

Click Refresh to re-gather the data from Cobra – for example, any updates in Cobra made since the record was created will now be reflected in the record.

The CAM can edit the SOW so that it can be updated into the control account tables.

With the Work Authorization having a status of In Review, the source fields that have been setup as editable, in this case, the CA SOW, can be updated by the Control Account Manager.  

If the CAM has not approved the Work Authorization, they will receive an email and a dashboard alert every 3 days as a reminder. This is a result of the Reminder action on the Workflow Steps tab of Workflow Type Configuration.

If the CAM has not approved the Work Authorization by one day after the assignment due date, the CAM is notified 3 days after the due date and the manager (defined in the security administrator) of the CAM receives notification.  

These are a result of the Past due and Manager Escalation step actions on the Workflow Steps tab of Workflow Type Configuration.

If the CAM (or delegate) rejects the Work Authorization:

No assignment record is created for the PCA; however if they are the originator, they will be able to modify the Work Authorization. An alternative step action could be to send notification to the creator of the Work Authorization. In the default data, it is assumed the PCA is the person to resolve the issues that triggered the rejection.

When you click the Approve button, the following happens:

Step 2

PCA reviews the CAM's SOW

The PCA now sees the assignment record in the List View.

The Work Authorization is now enabled with editable source fields (because the status is In Review).

The Approve, and Reject buttons are now visible to the PCA.

If the PCA has not approved the Work Authorization, the following occurs:

These are a result of the step actions on the Workflow Steps tab of Workflow Type Configuration.

If the PCA (or delegate) rejects the Work Authorization:

All actions defined in Step 1 Submit to the CAM for update of SOW begin.

After the PCA approves the Work Authorization, the following occurs:

The Work Authorization becomes disabled and the Refresh, Reject, and Approve buttons disappear.

Step 3

PM and IPT Lead approval

The PM or IPT Lead now see their assignment record in the List View.

The Work Authorization is now enabled with editable source fields (because the status is In Review).

The Approve and Reject buttons are now visible to the PM and IPT Lead.

If either the PM or IPT Lead has not approved the Work Authorization, the following occurs:

These are a result of the step actions on the Workflow Steps tab of Workflow Type Configuration.  

If one of the assignees approves, they also receive all of the notifications until all assignees have approved.

If the PM or IPT Lead (or delegate) rejects the Work Authorization, the following occurs:

After the PM or IPT Lead approves the Work Authorization, the following occurs:

When the second person approves the Work Authorization, the following occurs:

The Work Authorization becomes disabled and the Refresh, Reject and Approve buttons disappear.

Update Source

The final step action on is Update Source. This process updates the SOW on the control account table with the information found in the editable source fields. For the Work Authorization, the SOW is written back to the control account table. If you use Cobra, you can easily verify the updated field by opening the project and accessing the note on the control account.