Staff Escalation Subtask

Use this screen to update staff escalation records or change the percent of escalation of staff salaries.

Escalation is based on hire date. A value of zero means that person had not been hired yet, and then would escalate at a given rate annually throughout the project. The escalation date is based on configured values, it could be an anniversary date or particular month.

Note: The employee rate is different for EAC and Budget. A budget starts utilizing an employee’s rate at the first period of the budget, but an EAC adjusts the employee’s rate to the current period of the EAC.

The following information displays on the Staff Escalation subtask.

Column Headings Description
Hide Row This check box reflects the Hide Row check box on the Staff Hours subtask.
Note: This column displays only if the Enable Subtask Row Hide check box is selected.
ID Type Use the drop-down list and select from either Employee, Generic Staff or Key Entry.
ID Click to search the ID of the resource.
Name Enter the name of the resource in this field.
Acct ID This column displays the labor account ID of the resource.

Click to search for the account ID.

Org ID This column displays the Org ID of the resource.
PLC This column displays the Project Labor Category of the resource.
Hr Rate This column displays the employee's rate per hour based on the current period of the budget.
Note: By default, the Hr Rate is displayed when Labor Suppression in Manage Users is set to OFF. You can set the Hr Rate to be displayed or not using the Project tab of Configuration Settings. When Labor Suppression is set to ON the Hr Rate is not displayed.
YY-MM-DD This column displays the staff escalation rate per a given period. Value of zero means the employee has not been hired yet.

Fill Subtask

The following are the fields that display for the Fill subtask.

Field Description
Start Period

Click to display the calendar and select a starting date to copy values from

End Period

Click to display the calendar and select an end date to copy values throughout.

Fill Values

If you click Fill Values, the value 33.000 is copied all the way through in that one record from the starting date to the end date.

Fill Rows

If you click Fill Rows, the value is copied in all rows and columns from start date to end date.

Fill Columns

If you click Fill Columns, all values in the selected column are copied into all the other columns, from start date to end date. This means the whole column is copied and not just the value in that cell.