Prerequisites for Administrators
Before you run the report, you must update the report tables for the reporting period. This process usually is completed on a weekly or monthly basis.
Perform the following steps:
- Compute Burden
- Compute Revenue
- Update Project Status Reports
- Create Project Report Tables (with Revenue Summary selected)
If you want to use budget data on the report, the following setup screens and processes should be run prior to updating and creating the project report tables:
If you are using Standard Budgeting (Budgeting and ETC module):
- Manage Project Total Budget or Manage Project Budgets by Period
- Update Budget Report Tables
If you are using Advanced Budgeting (Advanced Project Budgeting module):
- Manage Project Budgets and ETC
- Create PSR Budget Report Tables
If you are reporting a backlog, the Contract Value and/or Funded Value amounts must be entered on the Manage Modifications screen prior to updating and creating the project report tables.