Delete WBS Levels

Use the New Business Budgets screen to delete Work Breakdown Structure (WBS) levels.

To delete the work breakdown structure level for the new business budget:

  1. Click Planning > New Business Budgeting > Actions/Processing > New Business Budgets.
  2. From the New Business Budget Status table, select the WBS level that you want to remove, and click Delete.
    Important:
    • If the WBS has a child item, you have to delete from the lowest level first. You cannot delete from top level.
    • If you click a WBS line that has a status of Working or Complete and then click Delete, you are only deleting that budget. Deleting budgets does not mean you are deleting them from the structure.