OTB (Over Target Baseline)
A PMB resulting from a formal reprojecting by the contractor, with customer approval, which establishes budget allocation in excess of the Contract Budget Base (CBB). For more information, see the "Log Transaction Page of the Project Audit Wizard" topic.