Set Task Resource Progress Statuses as Default or Done

To use the Task resource progress status submodule, you must have access to Settings as defined in the Employee cross-company access submodule under Settings.

To set a task resource progress status as default or done:

  1. On the main toolbar, click Settings .
  2. In the left pane of the Settings screen, click Projects & Jobs > Task Resource Progress Status.
  3. Highlight the task resource progress status you want to set as default or done and then select the Default Status or Done Status checkbox, as applicable.