Display the Copy Budget From Dialog Box

Display this dialog box from the Budget form in the Projects hub.

  1. In the Navigation pane, click Hubs > Projects > Budget.
  2. On the Budget form, select the project for which you want to copy budget data.
  3. In the Project Structure dialog box, select a work breakdown structure (WBS) element for which you want to copy budget information. (If the Project Structure dialog box does not display automatically, click to display it.)

    You can only enter or copy budget information for WBS elements at the lowest level of the WBS.

  4. On the Actions bar, click Other Actions > Copy Budget From