Redistribute Planned Hours
Use the Redistribute Hours feature on the Labor tab of the Plan form to replace planned hours with actual hours and spread the difference into a selected future time range, or to change the planned hours value for a selected assignment range.
You can redistribute hours for any WBS element at any level of the structure if that element has resources assigned.
- Related Topics:
- Replace Planned Hours with Actual Hours for an Assignment Range
You can replace the original planned hours with the actual hours and spread the difference into a selected time range for any level of the project structure, as long as there are resources assigned to the level. - Change the Planned Hours for an Assignment Range
To change the planned hours value for individual resource assignments, check out the project, select the resource, and use the Redistribute Hours dialog box to make the changes.
Parent Topic: How to...