Display the Reassign Dialog Box in Resource View

You display the dialog box from the Resource View grid row for the assignment that you want to reassign.

  1. In the Navigation pane, select Resource Management > Resource View.
  2. Use a search to display, in the grid, the resource from whom you want to reassign plan hours to another resource.
  3. Do one of the following:
    • If you are reassigning a single assignment, expand the plan work breakdown structure (WBS) under the resource until the assignment is visible in the grid.
    • If you are reassigning all assignments under a parent WBS element, expand the WBS under the resource until that parent element is visible.
  4. Do one of the following:
    • If you are reassigning a single assignment, hover over that plan row and click at the end of the assignment row.
    • If you are reassigning all assignments under a parent WBS element, hover over the parent row and click at the end of the row.
  5. Click Reassign.