Delete the Contents of a Project Plan

If necessary, you can delete the contents of a project plan, including all resource, expense type, and consultant type assignments, the related planned hours or amounts, and the baseline plan, leaving the project with an empty plan.

[In 5.0 pub, replace Short Description with this one.] If necessary, you can delete the contents of a project plan, including all resource, expense type, consultant type, and unit assignments, the related planned hours, amounts, or quantities, and the baseline plan, leaving the project with an empty plan.

However, if actual job-to-date (JTD) hours or amounts exist for any of the assignments, those assignments remain in the plan along with the JTD data, though their planned hours and amounts are deleted.

[In 5.0 pub, replace the above paragraph with this one.] However, if actual job-to-date (JTD) hours, amounts, or quantities exist for any of the assignments, those assignments remain in the plan along with the JTD data, though their planned hours. amounts, and quantities are deleted.

To delete the contents of a project plan:
  1. In the Navigation pane, select Hubs > Projects > Plan.
  2. Select the project for which you want to delete the plan contents.
  3. On the Actions bar, click Check Out.
  4. On the Actions bar, click Other Actions > Delete Plan Assignments.
  5. When a confirmation message displays, click Delete to delete the plan contents.