Assigning Costs to an Activity
Use this procedure to assign costs to an activity.
To assign costs to an activity:
Define cost resources in a resource file.
Assign the resource file to the project.
Select the activity to which you want to assign costs.
On the Resources tab of the Activity Details dialog box, assign the cost resources to the activity.
Click Apply.
Related Topic
Related Procedures
- Defining Cost Resources
- Calculating Actual Activity Costs
- Entering Actual Activity Costs
- Assigning resource requirements to an activity
- Assigning Multiple Resources to Multiple activities
- Assigning a Calendar to an Activity
- Assigning a Calendar to a Relationship