Assign a Calendar to a Relationship Lag from the Activity Details Dialog Box
You can assign a calendar to a Relationship lag from the Activity Details dialog box.
To assign a calendar to a relationship lag from the Activity Details dialog box:
Take one of the following actions to display the Activity Details dialog box for either the predecessor or the successor activity:
- Double-click the activity.
- Right-click the activity, and click Edit Activity on the shortcut menu.
- Select the activity, and click Details on the Edit tab.
In the Activity Details dialog box, click the Relationships tab.
Select the relationship to which you want to assign a calendar.
From the Calendar column, select the calendar you want to assign to the lag associated with the relationship.
Click Apply.
Related Topic
Related Procedures
- Assign a Calendar to a Relationship Lag from the Network or Barchart View
- Assigning resource requirements to an activity
- Assigning Multiple Resources to Multiple activities
- Assigning Costs to an Activity
- Assigning a Calendar to an Activity
- Assigning Codes to an Activity