Schedule Menu Group

Use this menu group to define schedules of the processes that you can run in Open Plan.


Contents of the Processes Tab Schedule Menu Group

The Schedule menu group on the Processes tab contains options to define schedules of the processes that you can run in Open Plan.

Auto-Analyze

Use this option to automatically calculate time analysis whenever you make a date-related change to the project.

Calendar

By defining the days and hours during which work can be scheduled, calendars allow you to create a realistic project plan.

Lock Project

Use this option to temporarily lock a project while in Shared Mode so that other users can't make any changes.

Refresh

Use the Refresh option or press ALT + F5 in Shared Mode to refresh the current project data.

Resources

The purpose of resource scheduling is to calculate a project that takes into account the limited availabilities of resources as well as the durations, logical relationships, and the target dates of the activities.

Risk

Use the Risk option to perform a risk analysis using the Monte Carlo Simulation Technique.

Time

Time analysis is the process of determining the overall schedule of a project by calculating start and finish dates for each activity in the project.

Time Now

Use the Time Now option to control the status date to be used for progress calculations.