Add a Risk Fund Task

You can mark a task as a risk fund task in order to assign its value to the Budgeted Risk Fund.

For tasks marked “Risk Fund”, all job budget lines from the current job budget are summed up on the job register as the Budgeted Risk Fund amount.

To mark a task as a risk fund task:

  1. Go to the Job Cost workspace.
  2. Locate the task line that you want to mark as a risk fund task.
  3. Click the Risk Fund check box for the task line.
  4. Click Save.