Follow this procedure to check the Open Plan base resource records.
To check the Open Plan BSU records:
-
Open your project in a spreadsheet view (such as the Assignment Spreadsheet).
-
Right-click anywhere in the view and click
Preferences.
-
In the
Table Name drop-down list, select
Baseline Usage and click
OK.
-
Create a sort to view the data correctly using on
Activity ID,
Resource, and
Start Date.
Note: The Res Used amount displays in seconds. If you have 8 hours per day, you can divide the seconds by 4800. However, this is not really needed to check the dates.
-
Check if the start and finish dates match the values in the Cobra calendar.
-
If the start date value is the day after the period end date in the Cobra calendar, and the finish date value is the period end date in Cobra, the time-phase spread from Open Plan to Cobra will be exactly the same.