Use the Weekly Schedule submodule to modify the start and end dates of tasks.
To use Weekly Schedule, you must have access to
Scheduling as defined in User Access Rights under
Settings.
To modify the start and end dates of tasks:
-
On the main toolbar, click
Scheduling
.
-
In the left pane of the Scheduling page, click
.
-
Apply filters to resource data.
-
On the grid toolbar, click
Filter
.
-
In the Filter dialog box, select the filters that you want to use and click
Apply.
When they are selected or cleared, the filters are applied automatically.
-
In the grid, select a resource, and click
Show Booking Details
.
WorkBook displays the booking details subgrid.
-
In the subgrid, double-click the start date or end date cell of a task and select the new date.