Standard fields are used by PM Compass to provide functionality. For example, the standard fields Project, Control Account, Work Package, and Activity provide a search dialog. PM Compass updates the informational standard fields such as Created Date, Step, Closed, Stage, and Status Date. There are a large number of change management standard fields that are updated by PM Compass. See the table below for the full list of standard fields.
For more information on fields, see Adding and removing fields on a form.
Field Name |
Description |
Activity |
Use this field to select an activity from the Activity Search dialog box. It enables only after you select a work package. If you change the work package, the Activity field becomes blank. If you select an activity that is not associated with the values in the Control Account or Work Package fields then the system updates them. |
Allocate Management Reserve |
Use this field to specify whether Undistributed Budget or Management Reserve should be allocated in the amount of the change. This field is only used as a flag or indicator and does not allocate the management reserve. See Advanced Tab of the Change Request Form for more details about this field. See System Checks When a Workflow is Approved for more details about how this field is used in a system check. |
Assigned To |
This field allows you to specify the user and/or group to whom you will assign a record. When the workflow has steps, the values in this field can be edited until the workflow steps start. After that, those with access to the workflow can add values that apply when the next step starts. If additional users should be added to a step that is currently in progress, use the Reassign option in the Workflow List View. When the workflow does not have steps, you can assign values until the workflow is completed and closed. If more than one user is assigned, the first user to select the Complete option causes the workflow to close for all the users. You can click to display the User Search dialog box or to display the Group Search dialog box.
Assignment is another workflow type that PM Compass provides. You cannot access it in Workflow Type Configuration, but it is in the Alerts. PM Compass uses this workflow type to assist with the tracking and assignment of records to users. Every time you enter a user in the Assigned To field, PM Compass creates an internal “Assignment” child record for each user in the list. This occurs whether or not the workflow type uses steps. |
Category |
This field displays the workflow category. |
Change Log Comment |
Use this field to enter comments or notes about the change you propose or make. Any information you enter will update the Cobra Project Audit Log when the change request is re-classed to an approved budget class.
|
Change Class |
This field displays the change class used by the change request. It can also be used to generate a report by cost set. |
Change Number |
The change number is used to create the cost temporary (sandbox) project, class, and schedule baseline. When you first create a new record, the change number is the same as the system-generated change number. It is added to the class, cost set, project, and Open Plan baseline descriptions when it is different from the system change number. PM Compass does not generate a change number for a change management request type that can be a child of other workflows. Instead, it uses the parent change number. |
Closed |
This check box allows you to mark a record as closed. PM Compass marks a record as closed under the following conditions:
|
Closed Date |
This read-only field displays the date the record was closed. |
Control Account |
This field allows you to select a control account from the Control Account Search dialog box. It is enabled after you select a project. If you change the control account, the following standard fields become blank: Work Package and Activity. The source fields for the control account are refreshed. PM Compass displays the control account you select as a hyperlink for all workflow types. If you have access rights to view the cost analysis, it displays in a separate session. This hyperlink is still active even when the control account field is read-only. If the Control Account you select is not associated with the value in the Project field, PM Compass updates the project. For example, if the Project is SHIP and the control account you select belongs to Demo Advance then PM Compass updates the project from SHIP to Demo Advance. This is true when you have access rights to multiple projects. |
Cost Difference |
This field displays the difference, after processing, between the Total cost and Requested cost. |
Created Date |
Use this field to indicate the date that a record is created. |
Current Baseline Start/Finish |
These dates are from the source project and are the maximum start/finish date for all control accounts. See Understanding the Different Date Sets and Date Calculation Differences in Open Plan and PM Compass for more information on the dates displayed. |
Current Cost |
Use this field to view the projects original cost. This field is summed from the live project. |
Description |
This allows you to enter a narrative on the nature of the record. |
Due Date |
This field provides
the end date for the completion of a record. |
Explanation |
Use this field to provide information on why there is a difference between the Total cost and Requested cost. |
ID |
This displays a unique key field for each record.
|
Last Corrective Action |
This field automatically populates with the corrective action ID of the original corrective action from last period's Explanation of Variance that was copied to create the current corrective action. If the current corrective action is newly created, this field remains empty. |
Log Comment |
This text box is editable, so you can enter your comments or any notes about the change you propose or make. Any information entered in this field will update the Cobra Project Audit Log when the change request is re-classed to an approved budget class. |
Priority |
This drop-down list allows you to select the level of urgency for the record. It should display the priority options in the order that you set them in the List Tables. You can find the priority code tables in Administration » List Tables. |
Project |
This field allows you to select a project from the Project Search dialog box. If you select a different project, the following fields will become blank: Control Account, Work Package, Activity, and all source fields in the record. |
Rate File |
The rate file used to calculate the costs for data stored in the change class. |
Requested Baseline Start/Finish |
These dates are from the temporary (sandbox) project and are populated when you enter schedule information in the Change Details view. See Understanding the Different Date Sets and Date Calculation Differences in Open Plan and PM Compass for more information on the dates displayed. |
Requested Cost |
This field displays the amount or additional cost being requested in the change request. If the Load the Change into Cost System as group on the Change Details on Form tab in Workflow Type Configuration is:
|
Requested Forecast Finish |
Use this field to view the Requested Forecast Finish date. This data is from the temporary (sandbox) project. This field is populated when you enter schedule information in the Change Details view. |
Requested Forecast Start |
Use this field to view the Requested Forecast Start date. This data is from the temporary (sandbox) project. This field is populated when you enter schedule information in the Change Details view. |
Resolution |
This field allows you to enter a narrative on how you completed the record and on any other information that pertains to the record. |
Significant Change |
When this option is selected, and the class is a budget class, the changes are broken out and shown as individual entries on the IPMR CPR Format 3 report while non-significant changes are grouped together and displayed as "Others." When the record is complete, it becomes visible in the Cobra Project Audit dialog and includes the log comment and change number. |
Stage |
This field displays
the stage or status of an workflow type. It can have any of the
following values: Closed,
In-progress, or Suspended. |
Status Date |
This field displays the status date. |
Step |
This displays the current step of the workflow. It is 0 before the workflow is started, and incremented as the workflow progresses. |
Step Start Date |
This field displays the step start date. |
The system-generated change number is a 10-character number that cannot be edited in the form designer. It is used as the class ID. It does not change if the display change number is edited. This number is used as the name for:
See Change Number Prefix on the Change Details on Form tab of Workflow Type Configuration for more information about the display change number and the system-generated change number. |
|
Title |
This field allows you
to enter a title for the record. |
Total Cost |
Use this field to view the sum of the Current and Requested fields. If the Load the Change into Cost System as group on the Change Details on Form tab in Workflow Type Configuration is:
|
Work Package |
This field allows you to select a work package from the Work Package Search dialog box. It enables only after you select a control account. If you change the work package, the Activity field becomes blank. The source fields for the work package are refreshed. If you select a work package that is not associated with the values in the Project or Control Account fields then the system updates them. |