Project Workload report
unavailable in ajeraCore
Use this report to forecast future requirements and view past trends,
all in one report. The report displays contract remaining amounts for
phases, and it forecasts when those amounts will be spent. It builds the
forecasts using a straight-line estimate, and the start and end dates
assigned to the phase.
Note:
|
Entering an actual start or end date in the Project Command Center overrides the estimated start or end date in this report. From that point on, the report uses the actual date.
|
With this report, you can:
- Identify future revenue.
- See workload by company,
department, or principal.
- Determine your ability to
handle a new project according to the timeframe requested by the client.
- Select to show the effect of your Business Development pipeline
on future workload.
To see the information for each employee working on a project, print
the Employee Workload report.
Audience
Principal
Project manager
Accounting
Marketing
Producing the report
From the Reports
menu, click Project > Project
Workload.
Forecasting potential
workload
Along with future actual workload, you can also choose to review a factored
forecasted amount for work you are currently pursuing.
When working with the BD phase, you
enter your percent chance of winning the work (on the Marketing Info subtab
of the Business Development subtab). You also link the production phase
to the BD phase by selecting the BD phase in the Marketing Phase field
on the General subtab. Ajera then calculates the factored amount by multiplying
the percent chance of winning (as entered for the BD phase) by the proposed
contract amount and hours for the linked production phases.
For example, your
firm is trying to win a job which requires 300 hours of work. Your firm
is competing against two other firms, and it is a new client for all firms,
so you expect you have an even chance of winning - a 1 in 3 chance or
33%. That 33% appears as roughly 100 hours of potential work on the report.
It appears in green so you can easily distinguish projected work from
actual work.
When considering just one project, the potential workload projection
may seem overweighted. However, when the Project Workload report includes
many potential projects, all with different percent chances of winning,
this factored amount can provide a realistic forecast of future workload.
Including potential workload in the report
Click
(Customize) and do the following:
- In the Amount Type field,
select Hours.
- Select the Include
marketing effort (Ajera only) check box.
Report options
Company
|
Multi-company only. The report contains information for all companies in your organization, unless you select
a specific company in this field.
|
Project
|
The report contains information for all projects for the period selected,
unless you select a specific project in this field.
|
View as of
|
The report contains information up to today's date, unless you select
a different date in this field.
|
Customize options
Report title
|
You can change the title of the report.
|
Sort order
|
Sorts the report by project manager, billing manager, principal-in-charge,
project, project type, client, or department. If you use multi-company, you can also sort by company.
|
Period
|
Prints the report for the next consecutive six periods, either weeks
or months, from the View As Of
date.
|
Amount type
|
Prints either hours, spent amounts, or cost amounts
|
Limit by
|
Only prints projects associated with the project manager or principal-in-charge
who is producing the report. You can print all projects by selecting
No limit. If you use multi-company, you can also limit by company.
|
Project status
|
Prints all projects or projects of a specific status.
You can also select a status of Marketing.
|
Include overhead in cost
|
If selected, it includes overhead in the cost amount.
|
Include overhead projects
|
If selected, it includes overhead projects in the report.
|
Include marketing effort
|
Includes your open Business Development efforts. To calculate amounts for this
potential work, Ajera multiplies the contract amount entered on linked
production phases by the percent chance of winning the work.
|
Print graph
|
If selected, a graph of the information appears on the report.
|
Use drilldown
|
If you select this check box and you are sorting by something other
than project, the report summarizes information
based on the sort. If you clear the check box, projects are also displayed.
If sorting by project, selecting or clearing the check box displays
projects.
|
Print customize options on reports
|
If selected, it prints a list of the options that you select.
|
Report contents
Note: |
Information
for the Status through End
Date columns does not appear until
you are viewing the project or phase level of the report. The information
in the Remaining as of column
is based on the current date. Information in the columns to the right
of the Remaining as of column
is based on the View as of date
you selected on the report window. |
Project
|
The ID of the project
|
Description
|
The name of the project or phase
|
Status
|
The current status of the project:
A - Active
P - Preliminary
M - Marketing
W - Work hold
H - Hold
B - Billing hold
C - Closed
|
Start Date
|
The date work began on the project or phase
|
End Date
|
The date work was complete on the project or phase
|
Labor Budget
|
The amount budgeted for labor on the project or phase
|
Remaining as of
|
The amount of budgeted labor currently remaining as of the date you
produce the report. The amount remaining is calculated based on spent.
|
subsequent six weeks or months
|
The amount of budgeted labor for each of the next six weeks or months
starting with the current date or the date you entered in the View
As Of field on the report window. Depending on the starting date
of the reporting period, these columns can contain historical, current,
and projected amounts, which are displayed as follows:
Red - Prior historical amounts
Purple - Current amounts
Blue - Future projected amounts
|
Calculations
Ajera uses a straight-line method to spread the contract remaining amount
evenly across remaining days at the lowest phase level. It sums those
amounts to higher-level phases, projects, and then your portfolio of projects.
For example, if a phase has $10,000
remaining and is scheduled for 10 more days until completion, the spent
value appears as $1,000 per day for the next 10 days.
Graph
If there
are no spent amounts for the last period, the graph does not appear.
Colors
Red
|
Amounts that are actually spent
|
Blue
|
Forecasted amounts based on project manager estimates rolled up from
phases
|
Purple
|
A mix of actual spent and forecasted spent
For example, if you produce the report to show months and run it on
the 15th of the month, the report shows the amount spent for that month
through the 15th and the projected amount you will spend from the 16th
until the end of the month.
|
Green
|
A factored forecasted amount based on estimates rolled up
from production phases
|
See also
Producing reports
Using the reports toolbar
|
|