Contract
|
This column displays the selected contracts.
|
Structure elements
|
This column displays, for each contract, the bottom or top five elements for the selected structure and structure level. To focus your analysis, you can select one element or any set of elements that are listed together. To select a set of elements that are listed together, click and drag to make the selection.
Click
next to the first column heading to select the structure level for which you want to display top and bottom variances.
|
SV
|
This column displays the cumulative or current schedule variance amount or schedule variance percentage for each element.
|
CV
|
This column displays the cumulative or current cost variance amount or cost variance percentage for each element.
|
VAC
|
This column displays either the variance at completion amount or variance at completion percentage for each element.
|
SV,
CV,
VAC
(colored cells)
|
These performance indicator columns display color-coded performance and trend information based on the selected period for schedule variance, cost variance percentage, and variance at completion percentage, respectively.
The colors and arrows are determined by the change threshold settings that your wInsight system administrator establishes for each contract in wInsight. The colors indicate current or cumulative performance based on the thresholds, and the arrows indicate if that performance represents a significant positive or negative trend, compared to the prior period.
|