Use the Unit planning grid to view information about the various units associated with a plan. You can insert a unit into the Units Planning grid, and also copy and paste existing rows as you insert units. To do so, right-click the small arrow to the left of a row to access the pop-up menu. After you enter unit information, it may be necessary to shift data due to date or schedule changes. When you refresh rates for the plan on the Rates tab, all rate information and calculated numbers on the Units grid automatically update using the new rate.
To change the columns that display on this grid, use the Units Tab of Planning Grid Configuration. You can also "freeze" the columns that display on the grid.
Field | Description |
Plus sign or Minus sign
|
The + (plus) and - (minus) signs follow standard Windows User Interface Conventions. The + sign in a grid row indicates the task is a parent task that contains related child units. Click the
+ to view the child units. The + changes to a - when the child units are open. Click the - to close the child units.
|
Description
|
Enter an identifier for the WBS element.
This is also the field in which you
assign units. Click
Insert to insert a new row, then enter an identifier in this field or click
Search to select a unit from the Units lookup. The unit that you specify here is assigned to the WBS element in the row directly preceding it on this grid.
|
WBS Level
|
This field displays the level of the WBS element, as specified on the Labor tab.
|
Project
|
This field displays the project identifier, as specified on the Labor tab.
|
Phase
|
This field displays the phase identifier, as specified on the Labor tab.
|
Task
|
This field displays the task identifier, as specified on the Labor tab.
|
Account
|
This field displays the default account assigned to the unit. Click
Search and select an account from the Account Lookup to assign a different account to the unit.
If the account is a reimbursable or a direct billing account, Vision automatically calculates the billing amount.
|
Unit Number
|
This field displays the unit number of the unit specified in the
Description field.
|
Unit Table
|
This field displays the unit table associated with unit specified in the
Description field.
|
Vendor
|
This field displays the name of the vendor associated with this unit expense.
|
Start
|
This field displays the start date for the unit expense.
If you created the plan from an Opportunity template, the start date displays the start date that originated with the opportunity.
If the
Start date does not align with the start date of the child WBS level task, the date displays in blue. You must select the
Collapse Parent Dates option to collapse the dates before you can use the Schedule tab of Project Planning to schedule task dependencies.
|
Finish
|
This field displays the finish date for the unit expense.
Right-click to select
Set finish date by duration. The Duration dialog box displays. Enter the number of business days to use to set the finish date. Vision automatically adds the number of business days to the Start date.
If you created the plan from an Opportunity template, the finish date automatically displays the end date that originated with the opportunity.
If the
Finish
date does not align with the end date of the child WBS level task, the date displays in blue. You must select the
Collapse Parent Dates option to collapse the dates before you can use the Schedule tab of Project Planning to schedule task dependencies. See the Collapse Parent Dates field description for additional information.
|
Cost Rate
|
Cost rates represent your firm's cost to produce a service.
When you select a unit from the Unit Lookup, the cost rate associated with the unit in the Unit Table automatically displays in this field.
You can manually enter a cost rate in this field. Entering a new rate overrides the existing cost rate.
|
Billing Rate
|
Billing rates represent what the client will pay for the services your firm provides.
When you select a unit from the Unit Lookup, the billing rate associated with the unit in the Unit Table automatically displays in this field. The billing multiplier entered on the Rates tab will be applied on top of the billing rates specified in the Unit Table.
You can enter a billing rate in this field. Entering a new rate overrides the existing billing rate.
|
Planned Qty
|
Enter the planned quantity for the current unit. This is the number of units you estimate as necessary to complete work on the element.
You can also right-click this cell to access the options for spreading amounts across the grid.
|
Planned Cost
|
This field displays the Planned Cost amount. Vision calculates the Planned Cost based on the following:
Cost Rate * Planned Qty
|
Planned Bill
|
This field displays the Planned Billing amount. Vision calculates the Planned Billing amount based on the following:
Billing Rate * Planned Qty
|
Percent Complete Cost
|
This field displays the percent complete of unit costs for the WBS element in this row.
If the
% Complete Formula option selected on the General tab is:
- User-Entered Percent Complete, then you can enter a percent complete here.
- Any other setting, then this field is non-editable and Vision calculates the value for you.
|
Percent Complete Bill
|
This field displays the percent complete of unit billing for the WBS element in this row.
If the
% Complete Formula option selected on the General tab is:
- User-Entered Percent Complete, then you can enter a percent complete here.
- Any other setting, then this field is non-editable and Vision calculates the value for you.
|
Job to Date Qty
|
This field displays the Job to Date quantity for the current unit expense, resulting from unit expense postings.
|
Job to Date Cost
|
This field displays the Job to Date actual cost for the current unit expense, resulting from unit expense postings. You see a value in this field only if the current plan is mapped to the Info Center.
|
Job to Date Bill
|
This field displays the Job to Date actual billed amount for the current unit expense, resulting from unit postings. You see a value in this field only if the current plan is mapped to the Info Center.
|
Estimate to Complete Qty
|
This field displays the Estimate to Complete quantity for the current unit, resulting from unit postings.
|
Plan - Estimate at Completion Cost
|
This field displays the variance between the planned unit cost amount and the Estimate at Completion unit cost amount for the current WBS element.
|
Plan - Estimate at Completion Bill
|
This field displays the variance between the planned unit billing amount and the Estimate at Completion unit billing amount for the current WBS element.
|
Estimate to Complete Cost
|
This field displays the Estimate to Complete unit amount for the unit expense.
|
Estimate to Complete Bill
|
This field displays the Estimate to Complete billing amount for the unit expense.
|
Estimate at Completion Qty
|
This field displays the Estimate at Completion quantity for the unit expense.
|
Estimate at Completion Cost
|
This field displays the Estimate at Completion cost amount for the unit expense.
|
Estimate at Completion Bill
|
This field displays the Estimate at Completion billing amount for the unit expense.
|
Plan Estimate at Completion Qty
|
This field displays the planned Estimate at Completion quantity for the unit expense.
|
Plan Estimate at Completion Cost
|
This field displays the planned Estimate at Completion cost amount for the unit expense.
|
Plan Estimate at Completion Bill
|
This field displays the planned Estimate at Completion billing amount for the unit expense.
|
Baseline Qty
|
If this plan does not yet have a baseline version saved for comparison and analysis, this field is blank. If this plan does have a baseline version, this field shows the quantity estimated for the current unit at the time the baseline version of the plan was saved.
|
Baseline Cost
|
If this plan does not yet have a baseline version saved for comparison and analysis, this field is blank. If this plan does have a baseline version, this field shows the cost estimated for the current unit at the time the baseline version of the plan was saved.
|
Baseline Bill
|
If this plan does not yet have a baseline version saved for comparison and analysis, this field is blank. If this plan does have a baseline version, this field shows the billing amount estimated for the current unit at the time the baseline version of the plan was saved.
|
Planned Revenue
|
This field displays the revenue amount expected for the current WBS element.
|